California prompt payment act and retainage rules
California spreads its prompt payment rules across the Public Contract Code, the Civil Code, and the Business and Professions Code. Public work has a 5 percent retention cap, and since January 1, 2026 most private work does too.
In California, public owners must pay undisputed progress payments within 30 days or owe interest, and private owners must pay within 30 days of a payment demand or owe a 2 percent per month penalty. Primes pay subs within 7 days of receiving a progress payment. Retention (California's word for retainage) is capped at 5 percent on public works and, for private contracts entered on or after January 1, 2026, on most private works too. Public owners release retention within 60 days after completion; private owners within 45 days.
| Rule | Public work | Private work |
|---|---|---|
| Owner to prime | 30 days after an undisputed, properly submitted request (PCC 10261.5 state; PCC 20104.50 local) | 30 days after a payment demand, unless otherwise agreed in writing (Civil Code 8800) |
| Late payment charge | Interest at the legal rate in CCP 685.010(a), 10 percent per year | 2 percent per month penalty in place of interest |
| Prime to sub (progress) | 7 days after receipt (PCC 10262 for state jobs; B&P 7108.5 otherwise) | 7 days after receipt, unless otherwise agreed in writing (B&P 7108.5) |
| Retention cap | 5 percent of each payment and of the contract price (PCC 7201), with limited exceptions | 5 percent for contracts entered on or after January 1, 2026 (Civil Code 8811), with exceptions |
| Retention release to prime | 60 days after completion (PCC 7107) | 45 days after completion (Civil Code 8812) |
| Retention release to sub | 7 days after the prime receives it (PCC 7107) | 10 days after the prime receives it (Civil Code 8814) |
| Late retention charge | 2 percent per month | 2 percent per month |
| Dispute withholding limit | 150 percent of the disputed amount | 150 percent of the disputed amount |
| Securities or escrow | Yes, required in public contracts (PCC 22300) | Not provided by statute |
Public projects: payment deadlines
State agencies must pay an undisputed, properly submitted progress payment request within 30 days or pay interest at the legal rate in Code of Civil Procedure 685.010(a), which is 10 percent per year. Local agencies (cities, counties, districts) have the same 30 day rule under PCC 20104.50, and the contract must include that article or a summary of it. Under both statutes, an improper request must be sent back within 7 days with written reasons. If the agency takes longer than 7 days to return it, the extra days come off its 30 day window. Note that for local agencies, a "progress payment" excludes the retention portion of final payment, which follows PCC 7107 instead.
On state jobs, PCC 10262 requires the prime to pay subs within 7 days of each progress payment. For other work, B&P 7108.5 sets the same 7 day rule, allows withholding of up to 150 percent of a good-faith disputed amount, and adds a 2 percent per month penalty payable to the sub. It is also grounds for discipline by the Contractors State License Board.
Public retention: 5 percent cap and 60 day release
PCC 7201 caps retention at 5 percent of each payment and 5 percent of the total contract price for public works contracts entered on or after January 1, 2012, and the same cap flows down every tier. A sub cannot be held at a higher rate than the prime. Exceptions: a sub that was told at bid time that bonds would be required and then fails to furnish them, and specific projects that the awarding body finds "substantially complex" before bid, with the higher rate disclosed in the bid documents. Nobody can be required to waive the section.
PCC 7107 requires the public entity to release retention within 60 days after completion (defined as beneficial use and cessation of labor, acceptance, a 100 day stoppage, or a 30 day stoppage with a recorded notice). One exception: a state agency holding no more than 125 percent of the estimated value of the remaining work gets 90 days to release undisputed retention. The prime then has 7 days to pay each sub its share. Late retention costs 2 percent per month, attempted waivers are void, and the prevailing party gets attorney's fees. Under PCC 22300, public contracts must let the contractor substitute securities for retention or have retention paid into escrow, with the interest going to the contractor. A contractor that elects to earn interest on retention must, on request, give the same option to any sub performing more than 5 percent of its total bid.
Private projects: Civil Code 8800 to 8818
Unless otherwise agreed in writing, a private owner pays an undisputed progress payment within 30 days after the contractor gives notice demanding payment under the contract. The penalty for missing it is 2 percent per month on the amount wrongfully withheld, and the owner may withhold no more than 150 percent of a good-faith disputed amount. The words "unless otherwise agreed in writing" matter: a contract can set a different schedule, so read the payment article before you sign.
- Retention release: the owner pays retention within 45 days after completion of the work of improvement (Civil Code 8812). The prime pays each sub its share within 10 days after receiving it (Civil Code 8814).
- Late retention: 2 percent per month plus attorney's fees to the prevailing party (Civil Code 8818).
- New 5 percent cap: for private contracts entered on or after January 1, 2026, Civil Code 8811 caps retention at 5 percent of each payment and of the contract price, at every tier.
- Cap exceptions: a sub that fails to furnish bonds it was told about at bid time, and residential projects that are not mixed-use and do not exceed four stories.
The statutes above set timing after the prime receives money. They do not decide whether a pay-if-paid clause in a subcontract can shift the risk of owner nonpayment to the sub; that question turns on contract law and case law, so have counsel review the clause. See pay-if-paid vs pay-when-paid clauses explained.
Related California guides
Payment disputes often end up in lien and stop payment notice territory, covered in California mechanics lien law. See also California contractor license requirements, California prevailing wage, and the prompt payment act glossary entry. Smart Business Automator tracks retention by contract date, so jobs signed before and after the 2026 private cap are handled correctly; see construction accounts receivable automation.
Frequently asked questions
What is the maximum retention on a California public works project?
PCC 7201 caps retention at 5 percent of each payment and of the contract price, at every tier, except for subs that fail to furnish required bonds and projects formally found substantially complex before bid.
Does California cap retention on private projects?
Yes, for private contracts entered on or after January 1, 2026. Civil Code 8811 sets a 5 percent cap, with exceptions for unbonded subs that were told bonds were required and for non-mixed-use residential projects of four stories or less.
How fast must a California GC pay its subs?
Within 7 days after receiving a progress payment under B&P 7108.5 (PCC 10262 on state jobs), unless otherwise agreed in writing on work covered by 7108.5. Retention shares are due within 7 days on public work and 10 days on private work.
What is the penalty for late payment in California?
2 percent per month on private progress payments, on late retention, and on late sub payments under B&P 7108.5. Late public progress payments earn interest at the legal rate in CCP 685.010(a), 10 percent per year.
Can I get interest on retention on a California public job?
Yes. PCC 22300 requires public contracts to allow substitution of securities for retention or payment of retention into escrow, with the interest going to the contractor.
Sources
- California Public Contract Code 7201, retention limits (text via california.public.law, sourced from leginfo.legislature.ca.gov)
- California Public Contract Code 7107, release of retention
- California Public Contract Code 10261.5, state agency progress payments
- California Public Contract Code 20104.50, local agency progress payments
- California Public Contract Code 22300, substitution of securities
- California Civil Code 8800, private progress payments
- California Civil Code 8811, private retention cap
- California Civil Code 8812, 8814, and 8818, private retention release
- California Business and Professions Code 7108.5, payments to subcontractors
- California Code of Civil Procedure 685.010, legal rate of interest
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.