Vermont prompt payment act and retainage rules
Vermont's Prompt Payment Act, 9 V.S.A. §§ 4001 to 4009, treats public and private owners the same: 20 days to pay the contractor unless the contract says otherwise, 7 days to pay subs, and retainage released 30 days after final acceptance.
Vermont's prompt payment act sits in 9 V.S.A. chapter 102 and reaches every construction contract for work on Vermont real property. The definition of owner expressly includes the State, municipalities, and school districts, so one set of rules covers public and private jobs. Unless the contract says otherwise, the owner pays interim and final invoices 20 days after the end of the billing period or 20 days after the invoice is delivered, whichever is later (§ 4002(c)). The contractor then pays each sub within 7 days (§ 4003(c)), and retainage is due within 30 days after final acceptance (§ 4005(a)).
| Rule | 9 V.S.A. chapter 102 |
|---|---|
| Owner pays contractor | Strictly per the contract (§ 4002(a)). If no term, 20 days after the end of the billing period or delivery of the invoice, whichever is later (§ 4002(c)) |
| Contractor pays subs | 7 days after receiving each progress or final payment, or 7 days after the sub's invoice, whichever is later, notwithstanding any contrary agreement (§ 4003(c)) |
| Interest | Owner: from day 21 unless otherwise agreed. Contractor to sub: from the day after the due date. Rate tied to 12 V.S.A. § 2903 (§§ 4002(d), 4003(d)) |
| Litigation penalty | 1 percent per month on sums wrongfully withheld, plus attorney's fees to the substantially prevailing party (§ 4007) |
| Retainage cap | No percentage cap in the chapter; set by contract |
| Retainage release | Within 30 days after final acceptance; subs paid within 7 days after the contractor receives it (§ 4005(a), (c)) |
| Retainage on materials | No retainage on delivered, accepted materials covered by a manufacturer's warranty or graded to industry standards, with a narrow exception (§ 4005(e)) |
| Invoice errors | Must be raised in writing within 10 working days or are waived (§ 4004) |
Owner to contractor
Section 4002 starts with the contract. If the contract has payment terms, the owner must follow them strictly. If it is silent, the contractor may bill progress payments at the end of each billing period (the calendar month, unless the parties agree otherwise) and a final invoice on completion, and the 20-day default applies. Mail counts as delivered three days after it is sent (§ 4001(7)).
Interest on late owner payments starts on day 21, again unless otherwise agreed, at the rate "established by 12 V.S.A. § 2903(b)." That cross-reference is dated: § 2903 has been amended, and the current text puts the 12 percent per annum judgment lien rate in subsection (c). Read the current statute or ask counsel before you put a rate on an invoice. Separately, if the dispute goes to court or arbitration and the payer is found to have broken the chapter's payment terms, § 4007(b) adds a penalty of 1 percent per month on everything wrongfully withheld. Amounts tied to a good faith claim, such as defective work or slow progress, are not wrongfully withheld.
Contractor to subs, and what about pay-if-paid?
The sub rules carry the phrase "notwithstanding any contrary agreement," so they override the subcontract. Two duties stand out:
- Disclose the owner's due date: before the subcontract is signed, the contractor must tell the sub when the owner's payments are due. Get it wrong and the contractor must pay the sub as if the owner had met the 20-day defaults (§ 4003(b)).
- Pass money down in 7 days: the sub is owed the full or proportional amount received for its work 7 days after the contractor receives payment or the sub's invoice, whichever is later. Interest starts the next day (§ 4003(c), (d)).
- Trust funds: on private work, money received for a building project is held in express trust for the claims of those who worked on it, although no separate bank account is required. No express trust is required on federal, State, or municipal projects (§ 4005a).
The chapter does not use the words pay-if-paid. The 7-day duty is keyed to money "received," which works like pay-when-paid timing, while § 4003(a) says a sub that performs is entitled to payment from the party it contracted with. How a court would treat an express pay-if-paid clause against those sections is a question for counsel, not this page.
Retainage in Vermont
Vermont does not cap the percentage. It controls timing instead. Retainage due at final completion must be paid within 30 days after final acceptance, and the same 30 days applies when only the contractor is holding retainage from its subs. Each tier then has 7 days to pass it down. An owner, contractor, or sub that unreasonably withholds acceptance, or sits on retainage, faces the chapter's interest, penalty, and attorney's fee provisions (§ 4005(d)). Federal-aid contracts may vary the chapter where the funding terms require it (§ 4008).
Frequently asked questions
Does Vermont's prompt pay law apply to public projects?
Yes. 9 V.S.A. § 4001 defines owner to include the State of Vermont, its instrumentalities and subdivisions, municipalities, and school districts, so the same chapter covers public and private work.
How many days does a Vermont owner have to pay?
Whatever the contract says. If the contract has no payment term, payment is due 20 days after the end of the billing period or 20 days after the invoice is delivered, whichever is later.
How fast must a Vermont contractor pay subcontractors?
Seven days after receiving each progress or final payment, or seven days after receiving the sub's invoice, whichever is later. This applies notwithstanding any contrary agreement.
Is there a retainage cap in Vermont?
The prompt pay chapter sets no percentage cap. It requires release within 30 days after final acceptance and bars retainage on certain delivered, warranted materials.
What happens if a Vermont owner pays late?
Interest accrues, and in arbitration or litigation the tribunal adds a penalty of 1 percent per month on sums wrongfully withheld. The substantially prevailing party also recovers reasonable attorney's fees.
Sources
- Vermont General Assembly: 9 V.S.A. chapter 102, Prompt Payment Act (§§ 4001 to 4009)
- Vermont General Assembly: 12 V.S.A. § 2903, Duration and effectiveness (judgment lien interest)
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.