Washington prompt payment act and retainage rules
Washington's prompt pay rules are public works rules: RCW 39.76 (30 days, 1 percent a month), RCW 39.04.250 (10 days to subs), and RCW 60.28 (5 percent retainage, released 60 days after completion). Private jobs run on the contract, with one statutory exception for change orders.
Washington's prompt payment act for construction is a set of public works statutes. Under RCW 39.76.011, a public body pays interest of 1 percent per month (at least $1 a month) when it misses the contract date or, at the latest, 30 days after a proper invoice or receipt of the work. Under RCW 39.04.250, a contractor paid on a public work has 10 days to pay its subs. Public retainage is capped at 5 percent and is released 60 days after completion, once tax and lien clearances are in (RCW 60.28.011, 60.28.021). The prompt pay and retainage statutes reviewed here do not set general payment deadlines for private work, but the change order rule in RCW 39.04.360 reaches most private jobs.
| Rule | Public works | Private work |
|---|---|---|
| Owner pays prime | Contract date, but no later than 30 days after a proper invoice or receipt of goods or services, whichever is later; grant-funded: 30 days after the later of a compliant request or receipt of the funds (RCW 39.76.011(2)(a)) | Set by the contract; no general statutory deadline in the statutes reviewed |
| Interest on late owner payment | 1 percent per month, minimum $1 per month (RCW 39.76.011(1)) | Per contract |
| Prime pays subs | Within 10 days after receiving payment (RCW 39.04.250(1)) | Per contract |
| Late or wrongful withholding from subs | Interest at the highest rate allowed under RCW 19.52.025, plus costs and attorney fees (RCW 39.04.250(3)) | Per contract |
| Change orders for completed extra work | Issue within 30 days of completion and request; 10 days to flow to lower tiers; 1 percent per month if late (RCW 39.04.360) | Same rule, except private residential projects of 12 units or less (RCW 39.04.360) |
| Retainage cap | 5 percent of moneys earned; projects with federal transportation funds rely on the bond instead (RCW 60.28.011(1)) | No statutory cap in the statutes reviewed |
| Retainage release | 60 days after completion of all contract work, subject to lien claims and tax certificates (RCW 60.28.011(3), 60.28.021) | Per contract |
Public owner to prime under RCW 39.76
RCW 39.76.011 applies to every state agency, county, city, town, school district, and other public body. If the public body plans to withhold part of a public works payment for unsatisfactory performance or a noncompliant request, it must tell the prime in writing within 8 working days, stating why and what remedial action is needed. A defective notice means interest from the 9th working day. Once the prime fixes the problem, the withheld amount is due within 30 calendar days, with interest from day 31. Good faith disputes noticed in time, natural disasters, and a few other cases are excepted (RCW 39.76.020), and the prevailing party in a suit for this interest recovers reasonable attorney fees (RCW 39.76.040).
Prime to sub on public works
RCW 39.04.250 gives the prime, and any sub that gets paid for work it passed down, 10 days after receiving payment to pay amounts allowed for each sub's work. In a good faith dispute, the payer may hold back no more than 150 percent of the disputed amount, and parties outside the dispute must be paid in full and on time. If the prime finds a problem with a sub's work after billing the owner, RCW 39.76.011(2)(e) requires notice of the remedial action before the sub's payment is due, a copy to the contracting officer, and payment within 8 working days after the fix. Skip the notice and interest runs at 1 percent a month from the 8th working day.
Public retainage under RCW 60.28
- Cap: public improvement contracts must provide, and public bodies must reserve, retainage of no more than 5 percent of moneys earned. Any other reservation from a contractor's earnings is prohibited (RCW 60.28.011(1), (9)).
- Reduction: the contractor may ask at any time to reduce retainage to 100 percent of the value of the work remaining (RCW 60.28.011(3)).
- Where it sits: at the contractor's option, the public body keeps it in a fund, deposits it in an interest-bearing account with interest to the contractor, or escrows it in bonds and securities the contractor chooses (RCW 60.28.011(4)).
- Retainage bond: the contractor may post a bond for all or part of the retainage, and the public body must release the bonded amount within 30 days of accepting it (RCW 60.28.011(6)).
- Subs: a contractor may hold no more than 5 percent from a sub or supplier and must pay interest at the rate it earns on its own reserved funds (RCW 60.28.011(5)).
- Release: 60 days after completion of all contract work, subject to the 45-day lien notice period and certificates from Revenue, Employment Security, and Labor and Industries (RCW 60.28.011(3), 60.28.021).
Private work and pay-if-paid
Washington has no general private prompt pay statute in the code sections reviewed, so payment timing, retainage, and pay-if-paid clauses on private jobs come from the contract. The one exception is change orders. RCW 39.04.360 requires an owner to issue a change order for the undisputed amount of satisfactorily completed extra work within 30 days of the contractor's request, and since a 2024 amendment (Laws of 2024, ch. 199) each upper tier has 10 days to issue matching change orders down the chain. Late change orders accrue 1 percent per month. Private residential projects of 12 units or less are excluded.
Frequently asked questions
How long does a Washington public owner have to pay a contractor?
By the contract date, but no later than 30 days after receiving a properly completed invoice or the goods or services, whichever is later. Late payments earn 1 percent per month under RCW 39.76.011.
How fast must a Washington prime contractor pay subs on public works?
Within 10 days after receiving payment, under RCW 39.04.250. In a good faith dispute, no more than 150 percent of the disputed amount may be withheld.
What is the Washington public retainage limit?
Five percent of moneys earned, under RCW 60.28.011. Contracts funded with federal transportation money rely on the contract bond instead of retainage.
Does Washington have a private prompt payment law?
Not a general one in the statutes reviewed. Private payment timing and retainage come from the contract. RCW 39.04.360 does require timely change orders on private projects, except residential projects of 12 units or less.
When is public retainage released in Washington?
Sixty days after completion of all contract work, once the lien notice period has passed and the departments of Revenue, Employment Security, and Labor and Industries have issued their certificates.
Sources
- Washington State Legislature: RCW 39.76 (Interest on unpaid public contracts)
- Washington State Legislature: RCW 39.04.250 (payments to subcontractors on public works)
- Washington State Legislature: RCW 60.28.011 (retained percentage)
- Washington State Legislature: RCW 60.28.021 (release of retained funds)
- Washington State Legislature: SSB 6192, Chapter 199, Laws of 2024 (amending RCW 39.04.360)
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.