Virginia prompt payment act and retainage rules
Virginia splits its rules between the Virginia Public Procurement Act (Code §§ 2.2-4347 to 2.2-4356) for public work and Code § 11-4.6 for private work. Both now make most pay-if-paid clauses unenforceable, and public retainage is capped at 5 percent.
Virginia's prompt payment act rules turn on who the owner is. If the contract sets no date, a state agency's payment date is 30 days after a proper invoice or receipt of the work, whichever is later, and a local government gets 45 days (Code § 2.2-4347). Private owners must agree in the contract to pay within 60 days of an invoice for satisfactorily completed work (§ 11-4.6(B)(1)). On both sides, the prime generally has 7 days after it is paid to pay the sub, and payment from upstream is no longer a condition precedent for most subcontracts. Public retainage is capped at 5 percent (§ 2.2-4333).
| Rule | Public work (Va. Public Procurement Act) | Private work (Code § 11-4.6) |
|---|---|---|
| Owner pays prime | Contract date, or if none: 30 days for state agencies, 45 days for localities, after the later of proper invoice or receipt of goods or services (§§ 2.2-4347, 2.2-4352) | Contract must require payment within 60 days of an invoice for satisfactorily completed work; withholding notice due within 45 days (§ 11-4.6(B)(1)) |
| Interest on late owner payment | State agencies: prime rate (Wall Street Journal) on amounts unpaid 7 days after the payment date (§ 2.2-4355). Localities: finance charges up to 1 percent per month (§ 2.2-4352) | Interest penalties consistent with § 2.2-4355 (§ 11-4.6(B)(1)) |
| Prime pays subs | Within 7 days of receiving payment, pay the sub's share or give written notice of withholding; in any case liable within 60 days of the sub's invoice (§ 2.2-4354) | Earlier of 60 days after the sub's invoice or 7 days after the prime is paid; withholding notice within 50 days (§ 11-4.6(B)(2)) |
| Interest prime to sub | 1 percent per month unless the contract says otherwise (§ 2.2-4354(5)) | Interest penalties consistent with § 2.2-4355 |
| Pay-if-paid | Not a condition precedent to paying lower tiers; contrary terms unenforceable (§ 2.2-4354(1)) | Not a condition precedent unless the upstream party is insolvent or in bankruptcy (§ 11-4.6(B)(2)) |
| Retainage | No more than 5 percent on progress payments; applies to subcontracts too (§ 2.2-4333) | No statutory cap in § 11-4.6; set by contract |
| Escrow | Required bid option on certain local road, site, and utility contracts of $200,000 or more (§ 2.2-4334) | None in statute |
Public work: state agencies and localities
Article 4 of the Virginia Public Procurement Act sets the payment date as the date in the contract or, if none, the 30-day or 45-day default above. For state agencies, interest starts on amounts still unpaid 7 days after the payment date, at the prime rate as reported in the Wall Street Journal, capped by the rate under § 58.1-1812, and no interest runs on the portion actually in dispute (§ 2.2-4355). Localities must flag invoice defects within 20 days and, absent other contract terms, pay supplier finance charges of up to 1 percent per month when late (§ 2.2-4352).
Section 2.2-4354 requires every state and local construction contract to carry flow-down payment clauses. The prime must, within 7 days of being paid for a sub's work, either pay the sub's proportionate share or notify the agency and sub in writing why it is withholding. Under the current text, the prime is also liable for the sub's invoice within 60 days of satisfactory completion even if the public owner has not paid, with a 50-day deadline to give a detailed withholding notice. Interest to subs defaults to 1 percent per month, and the prime cannot bill that interest back to the owner. Each subcontract must flow the same terms to lower tiers.
Public retainage and escrow
- Cap: on public construction contracts with progress payments, the contractor gets at least 95 percent of the earned sum when due; no more than 5 percent may be retained. Subcontracts on public projects with similar progress payments follow the same rule (§ 2.2-4333).
- Escrow option: localities contracting directly for $200,000 or more of highway, street, bridge, parking lot, demolition, grading, paving, drainage, or water, gas, and sewer line work must offer an escrow account option in the bid proposal. The contractor must return the signed escrow agreement within 15 calendar days of notice or lose the option (§ 2.2-4334).
- Exclusions: the escrow section does not apply to railroads, transit, runways, dams, power systems, and a few other categories (§ 2.2-4334(C)).
- Interest: the § 2.2-4355 interest penalty does not apply to retainage before final payment is due, though interest under an approved escrow agreement is still allowed (§ 2.2-4355(D)).
Private work under § 11-4.6
Section 11-4.6 applies to construction contracts with owners other than public bodies. Each owner-GC contract must require payment within 60 days of an invoice following satisfactory completion of the invoiced work, and an owner that withholds must say why, in writing, within 45 days. The GC then pays its sub by the earlier of 60 days after the sub's invoice or 7 days after the GC is paid. The statute makes pay-if-paid clauses unenforceable unless the paying party upstream is insolvent or in bankruptcy. On non-single-family projects worth more than $500,000, every lower-tier subcontract must carry identical payment, notice, and interest terms. Section 11-4.6 says nothing about a retainage cap, so the contract controls the percentage.
Frequently asked questions
How long does a Virginia state agency have to pay a contractor?
The date in the contract, or if none, 30 days after the later of receiving a proper invoice or the goods or services. Interest at the prime rate starts on amounts still unpaid 7 days after that date.
Are pay-if-paid clauses enforceable in Virginia?
Mostly not. On public contracts, payment from the owner cannot be a condition precedent to paying lower tiers. On private contracts, the same rule applies unless the upstream party is insolvent or a debtor in bankruptcy.
What is the retainage limit on Virginia public projects?
Code § 2.2-4333 limits retainage to 5 percent of the earned sum on public construction contracts with progress payments, and the same limit applies to subcontracts on those projects.
How long does a Virginia private owner have to pay?
Code § 11-4.6 requires the owner-GC contract to provide for payment within 60 days of an invoice following satisfactory completion of the invoiced work, with any withholding notice due within 45 days.
Do Virginia localities pay interest on late bills?
Under § 2.2-4352, unless the contract says otherwise, a locality that misses the payment date pays the supplier's finance charges, capped at 1 percent per month.
Sources
- Code of Virginia § 2.2-4347: Definitions (payment date)
- Code of Virginia § 2.2-4352: Prompt payment of bills by localities
- Code of Virginia § 2.2-4354: Payment clauses to be included in contracts
- Code of Virginia § 2.2-4355: Interest penalty; exceptions
- Code of Virginia § 2.2-4333: Retainage on construction contracts
- Code of Virginia § 2.2-4334: Deposit of certain retained funds
- Code of Virginia § 11-4.6: Required contract provisions in construction contracts
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.