Nebraska prevailing wage and certified payroll
Nebraska does not publish prevailing wage rates or require state certified payroll. Instead, its statutes make public works bidders file a fair labor standards statement, and federally funded work still falls under Davis-Bacon.
Nebraska has no prevailing wage law in the usual sense: no state agency surveys wages, there is no rate book by county or trade, and no state certified payroll filing. What Nebraska does have is an older fair labor standards requirement in Nebraska Revised Statutes sections 73-102 to 73-104. Public bodies must require contractors bidding on public works to file a statement that they comply with fair labor standards, and every public works contract must say those standards will be maintained. The U.S. Department of Labor's state table lists Nebraska with a dollar threshold of "None." On federally funded or assisted jobs over $2,000, the federal Davis-Bacon Act applies on top of that.
| Rule | Nebraska |
|---|---|
| State wage schedule | None published; no state certified payroll filing |
| State statute | Neb. Rev. Stat. 73-102 to 73-104 (fair labor standards on public works) |
| Bidder filing | Statement of compliance with fair labor standards, filed with the public body |
| Contract clause | Every public works contract must provide that fair labor standards will be maintained |
| Standard | Wages and conditions paid by at least 50% of contractors in the same field |
| Enforcement | After a public hearing, a noncompliant low bid can be disqualified |
| Federal coverage | Davis-Bacon on federally funded or assisted construction over $2,000 |
| Federal payroll | Weekly certified payroll with signed Statement of Compliance; WH-347 optional |
How Nebraska's fair labor standards rule works
Section 73-102 puts the duty on the public body. The governing authority or purchasing agent must require every contractor bidding on public works to file a statement that it complies with fair labor standards, and must write a fair labor standards clause into each public works contract. Two limits come with it. A state agency cannot impose requirements under these sections that would increase the state's cost for materials, supplies, or services. And the section does not apply to governing authorities whose contracts already set their own hours of labor, rates of pay, and conditions of employment.
Section 73-104 defines the term. Fair labor standards means the scale of wages and conditions of employment paid and maintained by at least 50 percent of the contractors in the same business or field as the contractor filing the statement. There is no state rate sheet behind that number. It is a market test. A Nebraska Supreme Court annotation to the statute (Philson v. City of Omaha, 1958) reads it as allowing a requirement to pay no less than the going wage, but not a fixed sum that ignores the going wage.
Section 73-103 supplies the teeth. If a public hearing shows, to the awarding authority's satisfaction, that a low bidder who filed the statement has not complied with fair labor standards in its business, the low bid is disqualified and the work goes to the next lowest responsible bidder. Because the standard is set by what most of your competitors pay, a contractor paying far below the local market for a trade is the one at risk.
When Davis-Bacon applies in Nebraska
Davis-Bacon covers construction, alteration, or repair contracts over $2,000 for public buildings or public works that are federally funded or assisted. The Related Acts reach projects that get federal help through grants, loans, loan guarantees, or insurance. In Nebraska that can include a rural water system upgrade financed with a federal loan, a federal-aid road job let by a county, or a housing project with federal assistance. The rates come from the federal wage determination attached to the contract, and the Department of Labor publishes those determinations on SAM.gov.
- Weekly payroll: submit certified payroll for each week covered work is performed. The prime submits for its subs and answers for them.
- Statement of Compliance: each payroll is signed by the contractor or sub, certifying the records are complete and every worker got the required rate.
- Form: the WH-347 is optional. The required information is not.
- Records: keep payrolls and contract documents at least 3 years after all work on the prime contract is complete.
- Apprentices: reduced rates only for apprentices individually registered in a DOL-registered program, within the program's ratio.
- Overtime: prime contracts over $100,000 also carry CWHSSA overtime at 1.5 times the regular rate after 40 hours in a workweek.
How this differs from a full state prevailing wage law
In a state like Missouri or Montana, an agency publishes rates by trade and area, contractors file certified payroll with the public body, and underpayment brings per-worker daily penalties. Nebraska's statutes do none of that. There is no number to look up, no state payroll report, and enforcement runs through a bid disqualification hearing rather than wage audits. Federal Davis-Bacon, by contrast, gives you an exact rate per classification and a weekly paper trail. Say a Lincoln mechanical contractor bids a $1.2 million school HVAC replacement. If the district funds it locally, the contractor files the fair labor standards statement and pays market wages. If part of the money is federal, the same job needs the federal determination and weekly payroll for every week on site.
Neighboring states handle this differently, so compare Iowa prevailing wage rules and Kansas prevailing wage rules if you cross the line. For the rest of Nebraska, see Nebraska contractor registration, Nebraska lien rights, and Nebraska prompt payment. Smart Business Automator prepares weekly certified payroll for federally funded jobs from the same time entries you already collect. See certified payroll automation.
Frequently asked questions
Does Nebraska have a prevailing wage law?
Not a rate-setting one. Nebraska does not publish prevailing wage rates or require state certified payroll. Its statutes require public works bidders to file a fair labor standards statement and contracts to include a fair labor standards clause.
What does fair labor standards mean in Nebraska?
Section 73-104 defines it as the scale of wages and conditions of employment paid and maintained by at least 50 percent of contractors in the same business or field as the bidder.
Is certified payroll required on Nebraska public works?
Not by state law. Certified payroll is required weekly on federally funded or assisted construction over $2,000 under Davis-Bacon, and an owner's contract can require payroll reports on its own terms.
Can a low bidder lose a Nebraska public job over wages?
Yes. Under section 73-103, if a public hearing shows the low bidder has not complied with fair labor standards, its bid is disqualified and the award goes to the next lowest responsible bidder.
Sources
- Nebraska Legislature: Neb. Rev. Stat. 73-102
- Nebraska Legislature: Neb. Rev. Stat. 73-103
- Nebraska Legislature: Neb. Rev. Stat. 73-104
- U.S. Department of Labor: State prevailing wage laws
- U.S. Department of Labor: Davis-Bacon and Related Acts
- 29 CFR 5.5: Contract provisions and related matters (Cornell LII)
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.