Louisiana prompt payment act and retainage rules
Public entities in Louisiana owe a certified progress payment within 45 days, contractors and subs must pass payment down within 14 consecutive days, and public retainage tops out at 10 percent on jobs under $500,000 and 5 percent on larger ones.
Louisiana splits its prompt payment act rules across two titles. Title 38 governs public owners: La. R.S. 38:2191 makes a public entity pay a certified progress payment within 45 days, and R.S. 38:2248 caps retainage at 10 percent on public contracts under $500,000 and 5 percent on contracts of $500,000 or more. Title 9 governs the flow of money down the chain: under R.S. 9:2784, a contractor or sub that is paid must pay its own subs and suppliers within 14 consecutive days or face a penalty of one half of one percent per day, capped at 15 percent. That flow-down rule does not apply to residential property.
| Rule | Public work | Private work |
|---|---|---|
| Owner pays prime (progress) | Within 45 days after receiving a certified payment request (R.S. 38:2191(B)) | No general statutory deadline found; the contract controls |
| Owner final payment | Within 45 days after formal final acceptance and a clear lien certificate (R.S. 38:2191(B)) | Contract controls |
| Prime pays subs and suppliers | Within 14 consecutive days of receiving payment (R.S. 9:2784(C)) | Same 14-day rule, except residential property (R.S. 9:2784(D)) |
| Late payment cost | 0.5% per day, capped at 15%, plus reasonable attorney fees (R.S. 38:2191(B)) | 0.5% per day of the amount due, capped at 15%, plus attorney fees (R.S. 9:2784(C)) |
| Retainage cap | 10% under $500,000; 5% at $500,000 or more (R.S. 38:2248(A)) | No statutory cap found |
| Retainage release | After 45 days from recordation of formal acceptance (R.S. 38:2248(A)) | Contract controls |
| Waiver by contract | Not allowed (R.S. 38:2191(C)) | Not stated |
Public work: what the owner owes the prime
R.S. 38:2191(A) requires every public entity to promptly pay contract obligations, approved change orders included, when they come due. Progress and final payments are due on the dates the contract sets. Subsection (B) is where the teeth are. If a public entity fails, without reasonable cause, to make a progress payment within 45 days after it receives a certified request for payment, it can owe reasonable attorney fees plus interest. The same exposure applies to a final payment made more than 45 days after formal final acceptance and receipt of a clear lien certificate.
Interest under 38:2191(B) runs at one half of one percent per day, compounded daily, and the total cannot exceed 15 percent. There is a detail most primes miss: if the contractor collects that interest, it must share it with its subcontractors in proportion to the principal owed to each, within ten business days. Subsection (C) bars contract terms that waive these protections, and subsection (D) lets the contractor seek mandamus to force payment when nonpayment is arbitrary, up to the amount appropriated for the contract.
Retainage on Louisiana public contracts
R.S. 38:2248(A) sets the ceiling. On a public project under $500,000, the owner may hold no more than 10 percent of the contract price. At $500,000 or more, the ceiling drops to 5 percent. The owner may keep it until 45 days after recordation of formal acceptance, or until a notice of default. Say a school board awards a $1.2 million roof replacement. Retainage cannot exceed $60,000, and it should not sit past the 45-day lien period after acceptance is recorded.
- Punch list cap: once the work is accepted, the owner may not withhold more than the value of the punch list (38:2248(B)(1)).
- Punch list timing: if the owner occupies or uses the work, the punch list must reach the contractor within 10 days of substantial completion, and it can be amended within 14 days after it is given (38:2248(B)(2)).
- DOTD exception: the punch list rules do not apply to the Department of Transportation and Development (38:2248(B)(3)).
- Liquidated damages: on flood protection and coastal protection projects, liquidated damages may be withheld after the 45-day period (38:2248(C)).
Paying subs and suppliers under R.S. 9:2784
R.S. 9:2784(A) says a contractor that receives payment from the owner must promptly pay each sub and supplier in proportion to the work they completed, and each sub owes the same duty to its own tier. If only part of the owner's payment comes in, subsection (B) requires a prorated split of what was actually received. Subsection (C) sets the clock: failure to pay within 14 consecutive days of receipt, without reasonable cause, triggers a penalty of one half of one percent of the amount due per day, capped at 15 percent of the outstanding balance, plus reasonable attorney fees for collection. A claimant whose claim is found to lack merit can be hit with the other side's defense costs and fees.
Example: an electrical sub bills $40,000 on a commercial job and the GC is paid on the 1st. Payment to the sub is due by the 15th. If it goes 30 days past that, the penalty math reaches 15 percent of the balance, which is the cap. Track the date each owner check clears, because that is the date the 14 days run from.
Private work and pay-if-paid
Louisiana has no general private statute that sets when a private owner must pay the prime or how much retainage it may hold, based on the statutes reviewed here. The contract governs those terms. R.S. 9:2784 still covers the downstream flow on private commercial work, but subsection (D) excludes improvements to property used for residential purposes. Neither statute addresses whether a pay-if-paid clause is enforceable, so read the subcontract closely and compare it with a pay-when-paid clause.
Smart Business Automator logs the date each owner payment is received and the date each sub is paid, which makes the 14-day window easy to watch. See construction accounts receivable automation.
Frequently asked questions
How long does a Louisiana public entity have to pay a contractor?
Under R.S. 38:2191(B), a public entity that fails without reasonable cause to pay a progress payment within 45 days of receiving a certified request can owe interest and attorney fees. Final payment is tied to 45 days after formal final acceptance and a clear lien certificate.
What is the retainage limit on Louisiana public projects?
R.S. 38:2248(A) allows up to 10 percent on contracts under $500,000 and up to 5 percent on contracts of $500,000 or more.
How fast must a Louisiana general contractor pay subcontractors?
Within 14 consecutive days of receiving payment from the owner, under R.S. 9:2784(C). Late payment without reasonable cause carries a penalty of 0.5 percent per day, capped at 15 percent, plus attorney fees.
Does the Louisiana subcontractor payment law cover home building?
No. R.S. 9:2784(D) says the section does not apply to improvements to property used for residential purposes.
Can a public contract waive the Louisiana prompt payment rules?
No. R.S. 38:2191(C) says those payment provisions cannot be waived by contract.
Sources
- La. R.S. 38:2191, payments by public entities (FindLaw copy, current as of January 1, 2023)
- La. R.S. 38:2248, retainage on public works (FindLaw copy, current as of January 1, 2023)
- La. R.S. 9:2784, payment of subcontractors and suppliers (FindLaw copy, current as of January 1, 2023)
- Louisiana State Legislature: Louisiana Laws
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.