Maryland prompt payment act and retainage rules
Maryland runs two systems. State procurement contracts use the State Finance and Procurement Article: 9 percent interest on late State payments and 10 days for the prime to pay subs. Private jobs use Real Property § 9-301 and following: 7 days to pay subs and a 5 percent retainage cap on bonded contracts of $100,000 or more.
Maryland's prompt payment act rules depend on who the owner is. On State procurement contracts, State Finance and Procurement (SFP) § 15-103 sets a policy of paying within 30 days of a proper invoice, and § 15-104 adds 9 percent annual interest once a bill is unpaid past the statutory window. The prime then has 10 days to pay undisputed amounts to its subs under § 15-226. On private work, Real Property (RP) § 9-302 requires payment of undisputed amounts down the chain within 7 days, and RP § 9-304 caps retainage at 5 percent on contracts of $100,000 or more when 100 percent performance and payment security is in place.
| Rule | State procurement contracts | Private work (RP Title 9, Subtitle 3) |
|---|---|---|
| Owner pays prime | Policy: within 30 days after payment is due and a proper invoice is received; 15 days on small business reserve contracts (SFP § 15-103) | Per contract dates, then within 7 days after the date specified; if no dates, within 30 days after the occupancy permit or owner possession, whichever is earlier (RP § 9-302(b)(1)) |
| Interest on late owner payment | 9% per year, starting day 31 after the later of the due date or invoice receipt (SFP § 15-104) | Court may award interest from the date it finds the amount was due (RP § 9-303(b)) |
| Prime pays subs | Within 10 days of receiving a State progress or final payment (SFP § 15-226(c)) | Within 7 days of receiving each payment (RP § 9-302(b)(3)) |
| Penalty for late sub payment | Up to $100 per day, payment holds, or work suspension after the State's dispute process (SFP § 15-226(f)) | Injunction, interest, costs; attorney fees for bad faith (RP § 9-303) |
| Retainage cap | See the procurement contract and the procuring agency | 5% when 100% performance and payment security is furnished; contracts under $100,000 excluded (RP § 9-304) |
| Retainage release | See the procurement contract | Undisputed retention paid within 90 days after substantial completion (RP § 9-304(e)) |
State procurement contracts: owner to prime
SFP § 15-103(a) states the State's policy to pay within 30 days after payment is due and a proper invoice is received, or within 15 days on small business reserve contracts. Section 15-104 is the money part. Interest accrues at 9 percent a year on an amount that is due and payable and still unpaid more than 37 days after the unit receives the invoice. Once triggered, it runs from the 31st day after the later of the due date or invoice receipt. Section 15-105 carves out exceptions that are not covered here, so read it before counting on interest.
These SFP rules cover State units. Counties, cities, and school boards may run their own payment rules, so check the local procurement code or the bid documents on county and municipal work.
State procurement contracts: prime to sub
SFP § 15-226 is a complaint process with a hard deadline. The prime must pay an undisputed amount to a sub or supplier within 10 days after it receives a State progress or final payment. If a sub sends written notice of nonpayment, the unit's representative must contact the prime within 2 business days, and if the amount is undisputed, the prime is told to pay within 3 business days. If payment still does not happen, the unit can hold further progress payments, stop processing payments until the sub is paid, suspend work, or impose a penalty of up to $100 per day. Every State procurement contract must also flow similar language down to subcontracts at each tier (§ 15-226(j)). Note that § 15-226(i) says these decisions are not subject to judicial review.
On contracts that carry payment security, SFP § 17-106 adds a certification: before each progress or final payment, the prime certifies in writing that suppliers were paid from earlier payments and will be paid on time from the current one. A false certification is a problem waiting to happen, so keep supplier payment records current.
Private work under Real Property § 9-301 and following
If the contract sets payment dates, the owner must pay undisputed amounts within 7 days after each date. If it sets none, payment is due within 30 days after the occupancy permit is granted or the owner takes possession, whichever comes first. A contractor or sub that is paid must pay its own subs within 7 days after receiving each payment for their work. RP § 9-302(b)(2) excludes contracts with the State, counties, municipal corporations, boards of education, and public authorities from those owner deadlines.
- Retainage cap: 5 percent of the contract price or payment when the contractor has furnished 100 percent performance and payment security, and a sub may not be held at a higher rate than the tier above (RP § 9-304(c)).
- Scope of the cap: contracts under $100,000 and contracts funded in whole or part by the Department of Housing and Community Development are excluded (RP § 9-304(b)).
- Release: undisputed retention held by an owner must be paid within 90 days after substantial completion (RP § 9-304(e)).
- Excess retention: retention above the cap counts as an undisputed amount, so it is subject to the 7-day payment rule (RP § 9-303(a)).
- Residential carve-outs: the subtitle does not apply to construction and sale of a single-family home, Custom Home Protection Act deals, or licensed home improvement contracts (RP § 9-305).
Remedies are court-driven: an injunction, interest from the date the court finds the money was due, and costs. Attorney fees are available when the court finds an owner, contractor, or sub acted in bad faith in withholding undisputed amounts. The statutes reviewed here do not address pay-if-paid clauses directly; the 7-day clock starts on receipt of payment, so read what your subcontract says about payment from the owner.
Smart Business Automator tracks invoices, receipts, sub payments, and retainage by job so the 7-day, 10-day, and 90-day dates are visible. See construction accounts receivable automation.
Frequently asked questions
What interest does Maryland pay on late State payments?
SFP § 15-104 sets 9 percent per year on amounts due and unpaid more than 37 days after the unit receives the invoice, running from the 31st day after the later of the due date or invoice receipt. Section 15-105 lists exceptions.
How fast must a prime pay subs on Maryland State contracts?
Within 10 days after receiving a State progress or final payment, for undisputed amounts, under SFP § 15-226(c).
What is the Maryland private retainage limit?
RP § 9-304 caps retention at 5 percent when the contractor has furnished 100 percent performance and payment security. Contracts under $100,000 and those funded by the Department of Housing and Community Development are excluded.
When must retainage be released on a private Maryland job?
Undisputed retention held by an owner must be paid within 90 days after substantial completion under RP § 9-304(e).
Does the Maryland private prompt payment law cover home improvement work?
No. RP § 9-305 excludes home improvement contracts with licensed contractors, construction and sale of single-family homes, and Custom Home Protection Act transactions.
Sources
- Maryland General Assembly: State Finance and Procurement § 15-103
- Maryland General Assembly: State Finance and Procurement § 15-104
- Maryland General Assembly: State Finance and Procurement § 15-226
- Maryland General Assembly: State Finance and Procurement § 17-106
- Maryland General Assembly: Real Property § 9-302
- Maryland General Assembly: Real Property § 9-303
- Maryland General Assembly: Real Property § 9-304
- Maryland General Assembly: Real Property § 9-305
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.