Maryland mechanics lien law and deadlines
Maryland subs must send a notice of intent to claim a lien within 120 days after doing the work, and every claimant must file a petition in circuit court within 180 days after finishing. The right to enforce expires one year after that petition.
Maryland runs its mechanics lien process through the courts, not the land records. Instead of recording a lien claim, you file a petition to establish the mechanic's lien in the circuit court for the county where the land is located, within 180 days after your work is finished or materials furnished. Subcontractors have an earlier step: a written notice of intent to claim a lien, served on the owner within 120 days. The rules are in Real Property Article, Title 9, Subtitle 1.
| Step | Who | Deadline |
|---|---|---|
| Notice of intent to claim a lien | Subcontractors, including those furnishing materials | Within 120 days after doing the work or furnishing materials |
| Petition to establish lien | All claimants | Within 180 days after work finished or materials furnished |
| Where to file | All claimants | Circuit court for the county where the land is located |
| Enforce the lien | All claimants | Within 1 year from the day the petition was first filed |
| Public work bond suit | Unpaid suppliers on bonded public jobs | Unpaid 90 days after last work; lower tiers give notice within 90 days |
Who has lien rights in Maryland
Real Property 9-102 makes every new building, and every building repaired, rebuilt, or improved to the extent of 15 percent of its value, subject to a lien for work and materials, without regard to the amount. The list is long: well drilling, pools, fencing, landscaping and planting, grading and paving, building or landscape architectural services, engineering, land surveying, interior design by a certified interior designer for interior construction, and leased equipment with or without an operator.
That 15 percent test matters for small repair and service work. A $6,000 HVAC repair on a building worth $900,000 does not reach 15 percent of value, so lien rights may not exist at all. Price the credit risk on small jobs accordingly. Also note 9-102(d): once legal title passes to a bona fide purchaser for value before the lien is established, the property is out of reach. Filing the petition counts as notice to later buyers.
The 120-day notice to owner for subcontractors
Maryland's preliminary notice step comes late, not early. Under 9-104, a subcontractor is not entitled to a lien unless, within 120 days after doing the work or furnishing the materials, it gives the owner written notice of intention to claim a lien, substantially in the form printed in the statute ("Notice to Owner or Owner's Agent of Intention to Claim a Lien"). The notice states the total earned, the amount due and unpaid, and a description of the work, the timing, and who it was done for, and it is signed under penalties of perjury.
- Delivery: registered or certified mail, return receipt requested, or personal delivery to the owner by the claimant or its agent.
- Multiple owners: notice to any one owner is enough.
- Owner absent: the sub may post the notice on the door or front of the building, in the presence of a competent witness, within the same 120 days.
- Owner's response: after receiving notice, the owner may withhold the amount due the sub from payments to the contractor.
Because the 120 days run from when the work was done, a sub on a long job should consider notice on earlier work before the clock passes on it. A framing sub that started in January and finished in July is already past 120 days on its January work by late May.
Filing the petition and enforcing
Under 9-105, file with the circuit court clerk within 180 days after finishing. The petition must include your name and address, the owner's name and address, the work or materials and when they were furnished, who you worked for, the amount claimed less credits, a description of the land and building, and, for a sub, facts showing the 9-104 notice was properly served or posted. Attach an affidavit and the key documents (contracts, invoices) or explain why they are missing. The clerk dockets it as an action in equity.
Under 9-109, the right to enforce an established lien expires one year from the day the petition was first filed. Within that year, file a petition in the same proceeding to enforce the lien or to collect on any bond posted to release it.
Single-family homes built for the owner
For a single-family dwelling being built on the owner's land as the owner's own residence, a sub gets a lien only if it gives the 120-day notice and the owner has not already paid the contractor in full before receiving it. The sub's lien is also capped at what the owner still owes under the contract when the notice arrives. On custom homes, notice sent early in the job protects far more than notice sent at the end.
Lien waivers and pay-if-paid clauses
Maryland's strongest waiver rule is in 9-113. An executory contract between a contractor and a sub may not waive, or require the sub to waive, the right to claim a mechanics lien or sue on a contractor's bond. A pay-if-paid clause also cannot strip those rights. Any provision that tries is void as against public policy. Waivers given after the work, in exchange for payment, are a different matter and are governed by their wording, so use a conditional lien waiver until the money clears. The sections reviewed here do not prescribe a statutory lien waiver form.
Public projects: Maryland's Little Miller Act
Public property is protected by payment bonds under State Finance and Procurement 17-103. Construction contracts above the state small procurement amount require payment security of at least 50 percent of the total contract amount, and local bodies may require it on contracts over $100,000. Under 17-108, an unpaid supplier may sue on the security if not paid in full within 90 days after last supplying labor or materials. A supplier that contracted with a sub or sub-sub but not the prime must give the contractor written notice by certified mail within 90 days after last supplying. The same section bars waiving the right to sue on the bond in an executory contract.
See also the Maryland contractor license guide, Maryland prevailing wage, and Maryland prompt payment rules. Smart Business Automator's accounts receivable automation can track 120-day and 180-day dates per job, so no unpaid invoice ages past them unnoticed.
Frequently asked questions
How long do I have to file a mechanics lien in Maryland?
File a petition to establish the lien in circuit court within 180 days after the work is finished or materials furnished. Subcontractors must also send the notice of intent to claim a lien within 120 days after doing the work.
Does a general contractor need to send a notice in Maryland?
The 120-day notice in Real Property 9-104 applies to subcontractors. A contractor working directly for the owner goes straight to the 180-day petition.
Can a subcontract waive Maryland lien rights?
No. Under 9-113, an executory contract cannot waive or require a sub to waive the right to claim a mechanics lien or sue on a contractor's bond, and pay-if-paid language cannot do it either.
How long does a Maryland mechanics lien last?
The right to enforce it expires one year from the day the petition to establish the lien was first filed, unless an enforcement petition is filed in that year.
Is every repair job lienable in Maryland?
No. A repaired or improved building is subject to a lien only if the work reaches 15 percent of its value. New buildings are covered regardless of amount.
Sources
- Maryland General Assembly: Real Property 9-102, buildings subject to lien
- Maryland General Assembly: Real Property 9-104, subcontractor notice
- Maryland General Assembly: Real Property 9-105, petition to establish lien
- Maryland General Assembly: Real Property 9-109, enforcement period
- Maryland General Assembly: Real Property 9-113, waivers void
- Maryland General Assembly: State Finance and Procurement 17-103, payment security
- Maryland General Assembly: State Finance and Procurement 17-108, suits on payment security
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.