What is a pay-when-paid clause in construction?
A pay-when-paid clause is a subcontract term that sets when the general contractor must pay the subcontractor, usually within a certain number of days after the GC receives payment from the owner. It controls timing, not whether payment is owed.
A pay-when-paid clause says the GC will pay the sub after the owner pays the GC, typically within a set number of days of receipt. Unlike a pay-if-paid clause, it does not make owner payment a condition of the debt. The sub is still owed the money. The clause only sets the schedule.
Many courts read pay-when-paid language to mean the GC must pay within a reasonable time even if the owner never pays. The clause buys the GC time to collect, not a permanent excuse.
Typical wording and what it means
A standard version reads something like: "Contractor shall pay Subcontractor within ten (10) days after Contractor receives payment from Owner for Subcontractor's work." Notice what is missing: there is no statement that the sub assumes the risk of owner nonpayment, and no "condition precedent" language. That is usually what separates pay-when-paid from pay-if-paid.
Public work often adds a statutory clock. On federal construction, FAR 52.232-27 requires the prime to pay subs within 7 days of receiving payment for their work, and late payment carries an interest penalty. Many state prompt payment laws set similar flow-down deadlines for public and sometimes private jobs.
How it works on a real job
Say a drywall sub bills $86,000 on its May pay application. The GC rolls it into the owner's pay app on May 25. The owner pays the GC on June 28. Under a 10-day pay-when-paid clause, the sub's payment is due July 8. If the owner pays late, the sub waits longer, but the money is still owed.
Now say the owner stops paying entirely in August. The GC argues it does not have to pay the sub until the owner pays. In many states, a court would say the GC got a reasonable time to collect, and once that time passed, the GC owes the sub regardless.
Common disputes
- Is it really pay-if-paid? GCs sometimes argue a timing clause shifts risk. The exact words decide it.
- What counts as payment for the sub's work? If the owner short pays the GC, the GC may claim the cut was for the sub's line items. Ask for the owner's approved pay app.
- Withholding for other reasons. GCs may offset back charges or retainage at a higher rate than the owner holds.
- Unknown payment date. Subs often have no idea when the owner paid. Ask for written notice of owner payment or check with the owner directly when the contract allows.
What subcontractors should negotiate
- An outside date: payment within a fixed number of days after the sub's invoice, regardless of owner payment.
- Written notice from the GC when the owner pays, or within a set number of days if the owner does not.
- Retainage held at no more than the rate the owner holds from the GC.
- Interest on late payment, matching the state prompt payment rate if there is one.
Related terms
Pay-when-paid clauses work alongside progress payments, the pay application, and lien waivers. See how to stop slow pay from general contractors and pay-if-paid vs. pay-when-paid clauses explained. Smart Business Automator shows when each pay app was billed and paid so the office knows exactly when payment is due. See construction accounts receivable automation.
Frequently asked questions
Does pay-when-paid mean I only get paid if the owner pays?
Usually not. Most courts treat it as a timing clause and require payment within a reasonable time even if the owner does not pay. A pay-if-paid clause is what shifts that risk.
How many days after owner payment must a GC pay a sub?
Whatever the subcontract says, subject to any prompt payment law. On federal construction, FAR 52.232-27 requires payment within 7 days of the prime's receipt.
Can a GC hold more retainage than the owner holds?
Sometimes, depending on the contract and state law. Negotiate retainage no higher than the owner's rate.
What should a sub do if the GC says the owner has not paid?
Ask for the owner payment status in writing, check the subcontract for outside dates, and keep lien and bond rights alive with timely notices.