What is a daily report in construction?
A daily report is the end-of-day record of what happened on a job site: who was there, what got done, what was delivered, the weather, and anything that slowed the work. The superintendent or foreman fills it out each workday, and subcontractor foremen often submit their own. Many companies use daily report and daily log interchangeably.
A daily report (also called a daily log, daily, or superintendent's report) is filled out by the superintendent or foreman each workday. It captures the facts of the day while they are fresh: crews and headcount by company, work completed by area, equipment on site, deliveries, inspections, visitors, weather, safety issues, and delays. On most contracts it is the first document anyone pulls when a dispute about time or cost comes up, because it was written on the day, not reconstructed later.
What a good daily report includes
- Weather: conditions at start and during the day, and whether work was lost.
- Manpower: each company on site, headcount, and hours.
- Work performed: by location or activity, tied to the schedule where possible.
- Equipment: what was on site, used, idle, or broken down.
- Deliveries: what arrived, from whom, and anything short or damaged.
- Inspections and visitors: inspectors, owner reps, design team, with results.
- Delays and issues: what stopped or slowed work, who was notified, and when.
- Safety: incidents, near misses, and toolbox talks.
- Photos: dated and located, especially of anything that could become a claim.
Example entry
Here is how a superintendent on a four-story wood-frame apartment job might write up a Tuesday:
| Field | Entry |
|---|---|
| Weather | Rain 6 a.m. to 10 a.m., then clearing. Exterior framing stopped until 10:30. |
| Manpower | Framing sub 12, plumbing sub 4, GC labor 2 |
| Work performed | Level 3 interior walls, grid C to F. Plumbing rough on level 1, units 101 to 104. |
| Deliveries | Level 4 floor trusses. Two trusses cracked, rejected, photos attached. |
| Inspections | Level 1 plumbing rough passed for units 101 and 102. 103 and 104 rescheduled. |
| Delays | RFI 22 on level 3 shear wall nailing still open, crew skipped grid D. PM notified at 2 p.m. |
Three weeks later the owner questions why level 3 framing ran long. The dailies show four mornings of rain, two rejected trusses that delayed level 4, and an open RFI that left a gap in the framing. That is the backbone of a time extension request, and it was written on the day.
Subcontractor foremen benefit from keeping their own dailies too, even when the GC does not ask. A sub's daily is the record of its own delays, out-of-sequence work, and extra work ordered in the field, and it is often the only record that tells the sub's side of the story.
Common mistakes
- Writing "same as yesterday" or skipping days. Gaps look bad in a dispute.
- Logging only your own crew and not the subs on site.
- Opinions and blame instead of facts. Write what happened, not who is incompetent.
- Photos with no date or location, which makes them much less useful.
- Filling reports in at the end of the week from memory.
Related terms
See daily log, field report, weather delay, and delay claim. Use the construction daily report template or read how to automate construction daily reports. Smart Business Automator summarizes daily logs across jobs so PMs and owners see the day's issues without reading every report.
Frequently asked questions
Is a daily report the same as a daily log?
Mostly. Many companies use the terms interchangeably. Some use daily log for the super's running notes and daily report for the formal submitted version.
Who fills out the daily report?
Usually the superintendent for the GC. Subcontractor foremen often submit their own dailies to the GC, and many contracts require it.
Do daily reports have to be sent to the owner?
Some contracts require submitting them daily or weekly, especially on public work. Others just require keeping them. Check the contract's reporting section.
How long should daily reports be kept?
At least as long as claims or defect suits could be brought, which can be many years depending on your state. Many contractors keep them permanently in digital form.