What is weather delay in construction?
A weather delay is time lost on a construction project because conditions like rain, snow, wind, extreme heat, or cold made work unsafe or impossible, and whether it earns a time extension depends on the contract and whether the weather was unusual for that place and season.
A weather delay happens when conditions stop or slow work on the critical path. A crew cannot pour a slab in a downpour, set steel in high wind, or put down asphalt on frozen ground. The hard part is not deciding whether it rained. It is deciding who carries the time. Most contracts expect contractors to plan for normal weather and give time only for weather that is worse than normal.
That makes weather delay a classic excusable delay: the contractor usually gets more time but not more money, and avoids liquidated damages for those days.
How weather delays work under the contract
On federal fixed-price construction, FAR 52.249-10 lists unusually severe weather among the unforeseeable causes beyond the contractor's control that excuse delay. To protect that right, the contractor must notify the contracting officer in writing of the causes of delay within 10 days from the beginning of the delay, unless the contracting officer extends that period. An alternate version of the clause uses the phrase causes other than normal weather. Private contracts vary widely: some give time for any weather that stops work, some only for abnormal weather, and some set a number of anticipated weather days per month in the specifications.
Documenting a weather delay on a real job
Say a GC is framing a 30,000 square foot warehouse in March. The contract says time extensions are allowed only for weather days in excess of the anticipated weather days listed in the specs. The super logs every day:
| Item | Days |
|---|---|
| Anticipated weather days in the contract for March | 5 |
| Days lost to weather on critical path work | 9 |
| Excess weather days (claimed) | 4 |
For each of the nine days, the daily log shows the conditions, the time work stopped, which critical activities were affected, crew sent home, and photos. Rain on a day the crew was working inside would not count, because it did not delay the critical path. The GC sends written notice within the contract deadline and requests a four-day extension with the logs and local weather records attached.
Common mistakes and disputes
- No baseline for normal. If the contract does not define anticipated weather days, the parties argue later over what normal looks like. Settle it before signing.
- Counting non-critical days. A day lost on work with plenty of float does not extend the finish date.
- Late notice. Many contracts bar requests not made within a set number of days. Under the federal clause it is 10 days from the start of the delay.
- Ignoring after-effects. Mud days, dewatering, and cleanup after a storm can delay work longer than the storm. Document them too.
- Expecting money. Weather delay usually earns time, not cost. Protection, heating, and acceleration costs are typically yours unless the contract says otherwise.
Related terms
See delay claim, force majeure, critical path method, and recovery schedule. Smart Business Automator's daily logs record weather and lost time per job, which gives PMs the backup a weather extension needs.
Frequently asked questions
Do contractors get paid for weather delays?
Usually not. Weather is typically an excusable but non-compensable delay: the contractor gets more time and avoids liquidated damages, but absorbs the cost. The contract controls.
What counts as unusually severe weather?
Weather that is worse than what is normal for that location and time of year. Contracts often define this using historical data or anticipated weather days in the specifications.
How do I prove a weather delay?
Daily logs showing conditions and lost work, photos, schedule updates showing critical path impact, and weather records for the job location. Give written notice within the contract deadline.
What is the notice deadline for weather delays on federal jobs?
Under FAR 52.249-10, the contractor must notify the contracting officer in writing of the causes of delay within 10 days from the beginning of the delay, unless the contracting officer extends the period.