Scheduling

What is float in construction?

Float (or slack) is the amount of time an activity can be delayed without pushing back the project's completion date or, for free float, the next activity. Activities on the critical path have zero float. Negative float means an activity is already behind a required date. Many specifications say float belongs to the project, so either party can use it.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

In a critical path method schedule, float is the cushion between when an activity can happen and when it must happen. Activities on the critical path have zero float: any slip moves the finish date. Activities off the critical path have some float, measured in work days, and can slide within it without hurting completion. Float is also called slack, and you will see it called schedule float in some specs.

Total float and free float

Two kinds of float
TypeDefinitionPractical meaning
Total floatLate finish minus early finishDays the activity can slip before the project end date moves
Free floatEarly start of the next activity minus early finish of this oneDays it can slip before it delays the very next task

An activity can have total float but no free float. It will not delay completion, but it will push the next trade, which may cause a cascade of crew moves even if the end date holds.

How float works on a real job

On a 14-week medical office fit-out, the low-voltage cabling activity is scheduled for weeks 6 and 7. Ceiling close-in, the next activity that depends on it, is not needed until week 10. Completion depends on drywall and finishes, not cabling. The schedule shows cabling with 15 work days of total float and 15 days of free float.

The low-voltage sub's crew is pulled to another job and starts a week late. Five days of float are used up. The finish date is fine, and ceilings still close on time. But now cabling has only 10 days left. If the owner then adds 40 data drops, the extra work may eat the rest, and cabling joins the critical path. That is why float is tracked every update, not just at baseline.

Who owns the float

This is the classic float dispute. If the owner's late equipment decision uses up float, and then the contractor's own slow crew causes a delay, who is responsible for the late finish? Contracts answer it in different ways:

  • Project float: float belongs to the project and is available to whichever party needs it first. This is common in specifications.
  • Contractor float: the contractor's planning created the float, so the contractor controls it. Less common in owner-drafted contracts.
  • Silent contract: courts and arbitrators sort it out, which is expensive. Read the scheduling spec.

Common mistakes

  1. Hiding float with preferential logic or constraints so the owner cannot use it. Schedulers spot it, and it damages credibility in a delay claim.
  2. Treating float as free time. Burning it early leaves nothing for problems later.
  3. Ignoring near-critical activities with only a few days of float.
  4. Not recording who used float and why in each update narrative.

Related terms

Float ties into the baseline schedule, Gantt chart, recovery schedule, and excusable delay. For updating practice, see how to update a construction schedule every week.

Frequently asked questions

What does negative float mean?

The activity is already behind the date needed to meet a required finish or milestone. Negative float shows how many days must be recovered.

Is float the same as slack?

Yes. Float and slack mean the same thing in scheduling.

Can the owner use the contractor's float?

It depends on the contract. Many specifications say float belongs to the project, which means either party can use it as long as it lasts.

How is total float calculated?

Late finish minus early finish (or late start minus early start), calculated by the scheduling software from the forward and backward passes.

Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.

Get a free assessment