Submittal log template
A submittal log tracks every shop drawing, product data sheet, and sample from the day it is due to the day it comes back approved. Download this template as a CSV or print it.
A submittal log template is a running list of every submittal on a job: what it is, which spec section requires it, who owes it, when it went to the architect, when it came back, and what the reviewer said. The free template below gives the general contractor one sheet to see what is late, what is in review, and what has to be released before materials can be ordered.
Most material delays start on paper. The storefront has a long lead time, the shop drawings sat in a sub's inbox for three weeks, and nobody noticed until the opening was framed and empty. A submittal log reviewed every week is how you catch that early.
What the submittal log is for
The specifications list the submittals each section requires: shop drawings, product data, samples, mock-ups, test reports, and closeout items. At the start of the job, the GC builds the log from the specs, assigns each item to a sub or supplier, and sets a required date working back from when the material has to be on site. Then the log tracks each item through review and resubmittal until it is approved and released for fabrication.
How to fill in each column
- Submittal number: many teams use spec section plus a sequence, like 08 41 13-01, so related items group together.
- Spec section and description: what the item is and where the spec requires it.
- Responsible sub or supplier: who prepares it.
- Required by: the date it must be approved, worked back from the install date minus fabrication and delivery time.
- Date received from sub and date sent to architect: shows whether the delay is with the sub or the GC.
- Date returned: when the reviewer sent it back.
- Status: use the review stamp wording on your job, such as approved, approved as noted, revise and resubmit, or rejected.
- Lead time: the fabrication and delivery time after approval. This is what turns a late submittal into a late job.
Common submittal log mistakes
- Building the log from memory instead of reading every spec section, then discovering a missed submittal at closeout.
- Forwarding sub submittals to the architect without checking them against the specs first.
- No required-by dates, so everything looks equally urgent until it is too late.
- Ordering material on an "approved as noted" submittal without reading the notes.
- Not tracking resubmittals as new revisions, so it is unclear which version was approved.
Related forms and guides
See how to manage submittals on a construction project for the full process and how to manage long-lead items for the procurement side. Questions that come up during review usually become RFIs, so pair this log with the RFI template. Once material ships, track it in a material delivery log.
Smart Business Automator tracks submittals and RFIs by due date and links them to shipment tracking, so a late approval shows up against the delivery it will push. See RFI and submittal tracking automation.
Submittal log
| Submittal number | Spec section | Description | Responsible sub or supplier | Required by | Received from sub | Sent to architect | Returned | Status | Lead time after approval |
|---|---|---|---|---|---|---|---|---|---|
| 03 30 00-01 | 03 30 00 | Concrete mix designs | Ready-mix supplier | 2026-05-15 | 2026-05-05 | 2026-05-06 | 2026-05-12 | Approved | 1 week |
| 05 12 00-01 | 05 12 00 | Structural steel shop drawings | Steel fabricator | 2026-05-29 | 2026-05-14 | 2026-05-15 | 2026-05-27 | Approved as noted | 6 weeks |
| 08 41 13-01 | 08 41 13 | Aluminum storefront shop drawings and finish samples | Glazing sub | 2026-06-05 | 2026-05-28 | 2026-05-29 | 2026-06-09 | Revise and resubmit | 10 weeks |
| 08 41 13-01 R1 | 08 41 13 | Aluminum storefront, resubmittal | Glazing sub | 2026-06-05 | 2026-06-12 | 2026-06-12 | In review | 10 weeks | |
| 09 30 00-01 | 09 30 00 | Porcelain tile product data and samples | Tile sub | 2026-06-19 | Not received | 3 weeks | |||
| 23 37 13-01 | 23 37 13 | Diffusers, registers, and grilles product data | HVAC sub | 2026-06-26 | 2026-06-10 | 2026-06-11 | In review | 4 weeks |
- Sample data only. Spec sections follow the MasterFormat numbering used on many commercial jobs; use your project's spec book.
- Set Required by working back from the install date: install date minus lead time minus review time.
- Log a resubmittal as a new revision (R1, R2) on its own row so the history is clear.
- Use the exact status wording from the architect's review stamp.
- Review the log weekly, sorted by Required by.
Frequently asked questions
What is a submittal log in construction?
A list that tracks each required submittal from the specs through preparation, review, and approval, with dates and status for each.
Who maintains the submittal log?
Usually the general contractor's project manager or project engineer. Subs prepare the submittals; the GC checks, forwards, and tracks them.
How is a submittal different from an RFI?
A submittal shows how the contractor plans to meet the design, such as shop drawings or product data. An RFI asks a question about the design itself.
Can I use this submittal log in Excel?
Yes. Download the CSV, open it in Excel or Google Sheets, and add conditional formatting to highlight items past their required-by date.