What is a submittal schedule in construction?
A submittal schedule is a dated plan for every required submittal on a project, working backward from when the material is needed on site to set when each submittal must be sent, reviewed, and approved. The GC's project engineer or PM usually prepares it, often shortly after notice to proceed. The submittal log records what actually happened.
Every submittal, whether shop drawings, product data, samples, or mock-ups, has to be approved before the material can be ordered, and some materials take months to make. The submittal schedule ties those two facts together. For each item it lists the date the material must be installed, subtracts fabrication and delivery time, subtracts review time, and arrives at the date the submittal has to go out. Many contracts require the GC to provide one early in the job, and the architect uses it to plan review staffing.
It is related to, but different from, the submittal log. The log tracks what happened. The schedule says what has to happen and when.
How to build one
- List every required submittal from the spec sections. Each section usually has a submittals paragraph.
- Find the need date for each item from the construction schedule: when does the material have to be on site?
- Back out the lead time from the supplier: fabrication plus shipping.
- Back out review time as the spec defines it, plus a resubmittal cycle for anything complex.
- Back out preparation time for the sub or supplier to put the package together.
- Assign a responsible party and send each sub its dates as part of the subcontract or kickoff.
A worked example
On a 3-story lab building, the curtain wall must start installation on August 4. The glazing sub says fabrication and delivery take 14 weeks after approved shop drawings. The spec allows the architect 15 working days per review, and the GC plans for one resubmittal.
| Step | Duration | Date |
|---|---|---|
| Install start | August 4 | |
| Fabrication and delivery | 14 weeks | Approval needed by April 28 |
| Resubmittal review | 15 working days | Resubmit by April 7 |
| Sub revises comments | 1 week | First review back by March 31 |
| First review | 15 working days | Submit by March 10 |
| Shop drawing prep | 4 weeks | Sub starts by February 10 |
The project kicked off January 20. That leaves three weeks before the glazing sub has to start drawings, so the curtain wall subcontract has to be signed in that window. The schedule just made buyout urgent.
Common mistakes
- Building the schedule from spec order instead of construction need. Section 03 is not always the first need.
- Assuming every submittal is approved on the first try. Complex packages usually come back at least once.
- Forgetting submittals that depend on others, such as hardware schedules that wait on door shop drawings.
- Not linking it to the construction schedule, so when the job moves the submittal dates do not.
- Sending everything at once. A wall of submittals in week 3 overloads the reviewers and slows the critical items.
Related terms
See shop drawings, expediting, and how to manage submittals on a construction project. Smart Business Automator tracks submittal due dates, review status, and shipments by job; see RFI and submittal tracking automation.
Frequently asked questions
What is the difference between a submittal schedule and a submittal log?
The schedule plans when each submittal must be sent and approved. The log records what was actually sent, when, and what came back. Many teams keep both in one register.
Who prepares the submittal schedule?
Usually the general contractor's project engineer or project manager, with lead times and prep durations from each subcontractor and supplier.
How much review time should a submittal schedule allow?
Whatever the specifications set for the architect and engineers, plus time for at least one resubmittal on complex items.
When is the submittal schedule due?
Many contracts require it shortly after notice to proceed. Check the general requirements section of the specifications for the deadline on your job.