West Virginia prompt payment act and retainage rules
West Virginia's Prompt Pay Act of 1995 gives counties and municipalities 60 days to pay a legitimate uncontested invoice, with interest starting on day 61. The code sections reviewed here set no retainage cap, no prime-to-sub payment deadline, and no private-project prompt pay rule, so the contract does most of the work.
West Virginia has a thin prompt payment act compared with most states. The main statute is the "Prompt Pay Act of 1995," which appears twice in the code: W. Va. Code § 7-5-7 for counties and § 8-13-22d for municipalities. Each gives the local government 60 days after it receives a legitimate uncontested invoice to issue a check, and interest runs from the 61st day at a rate set by the State Tax Commissioner. State agency purchases fall under a separate section, W. Va. Code § 5A-3-54, which this page does not summarize. The code sections reviewed for this page set no cap on retainage, no deadline for a prime to pay its subs, and no prompt pay rule for private jobs.
| Rule | Public work | Private work |
|---|---|---|
| Owner pays prime | Counties and municipalities: check within 60 days after a legitimate uncontested invoice is received (§ 7-5-7, § 8-13-22d) | No statute found; contract terms govern |
| Interest on late owner payment | From day 61 at the State Tax Commissioner rate under § 11-10-17a, unless payment is blocked by unforeseen budgetary constraints | Contract terms |
| Prime pays subs | No statutory deadline in the sections reviewed | No statutory deadline |
| Retainage cap | None found in the code sections reviewed | None found |
| Retainage release | Per contract; older state contracts (1969 to 1991) carried a 90-day final payment clause under § 14-3-1 | Per contract |
| Pay-if-paid | Not addressed by statute; a 2020 law firm survey lists it as permissible | Same |
County and municipal jobs: the 60-day rule
Both versions of the Prompt Pay Act protect any properly registered and qualified vendor that supplies services or commodities to the county or city, or to one of its agencies. A paving contractor billing a county commission fits. So does an HVAC firm billing a city water board.
- Deadline: the check must issue within 60 days after the invoice is received.
- When the invoice counts as received: the earlier of the date the agency stamps it received or the U.S. Postal Service postmark, unless the vendor can prove an earlier receipt date. If the invoice arrives before the work is done and accepted, the clock starts on acceptance instead.
- Processing: the agency that first receives the invoice has 10 days to process it for payment. Any other agency that has to handle the requisition must process or reject it for good cause within 10 days.
- Interest: a check issued after day 60 must include interest from day 61 until the check is mailed. The county sheriff or municipal treasurer deducts it from the account of the agency that caused the delay.
- Escape hatch: the section does not apply if payment cannot be made in 60 days because of unforeseen budgetary constraints.
The interest rate is not a fixed number. Section 11-10-17a tells the Tax Commissioner to set it each year at the adjusted prime rate charged by banks, rounded to the nearest hundredth of a percent, plus three percentage points, measured on the first business day of December and effective January 1. Look up the current year's figure with the West Virginia State Tax Department before you calculate a claim.
Example: an electrical contractor mails a $62,000 progress invoice to a city on May 2, and the city stamps it received May 5. The postmark date, May 2, is earlier, so that is the receipt date. Day 60 is July 1. A check mailed on July 20 should carry interest from July 2 (day 61) until it is mailed, unless the city can point to an unforeseen budget shortfall.
State agency and highway contracts
Section 14-3-1 required certain state construction contracts to say the balance would be paid within 90 days after completion was certified or accepted, the project was occupied, or it was dedicated for public use, whichever came first, with interest from day 91. Division of Highways road and bridge contracts used 150 days after written notice of final acceptance, with interest from day 151. Read the dates closely, though: the section applies to contracts entered into on and after March 1, 1969, and before July 1, 1991. For a current state job, start with the payment terms in your contract and the agency's specifications. State agency invoice payment is governed by W. Va. Code § 5A-3-54 (enacted in 1990 and amended in 2010); its text could not be retrieved for this page, so confirm its deadline and interest terms with the Purchasing Division before you rely on a date.
On state building contracts over $250,000, § 5-22-1 requires the apparent low bidder to list every sub that will do more than $25,000 of work, and the winner must furnish a performance and payment bond. For a sub on a public job with no statutory flow-down deadline, that payment bond is the main safety net when the prime is slow.
Subcontractors, retainage, and pay-if-paid
West Virginia's prompt pay sections only address the government paying its vendor. None of them tells the prime how fast to pay a sub, and none of them caps retainage. A Levelset retainage guide reaches the same conclusion, stating that the state has no retainage statute for public or private projects. That puts the burden on the subcontract: write in the retainage rate, a release trigger tied to your own scope where possible, and a payment deadline measured in days after the GC is paid.
The code also does not mention pay-if-paid clauses. Husch Blackwell's July 2020 state-by-state survey lists pay-if-paid as permissible in West Virginia. Because no statute sets the rule, the exact wording of the clause matters; have counsel review any clause that makes the owner's payment a condition of yours. Your lien rights may be the stronger tool on private work, so track the West Virginia mechanics lien deadlines from your first day on site.
Smart Business Automator logs the date each invoice went out and flags anything past 60 days, so the interest claim is ready when the check is late. See construction accounts receivable automation.
Frequently asked questions
How long does a West Virginia county or city have to pay a contractor?
Sixty days after it receives a legitimate uncontested invoice, under W. Va. Code § 7-5-7 (counties) and § 8-13-22d (municipalities). Interest runs from the 61st day unless unforeseen budgetary constraints prevent payment.
What interest rate applies to late public payments in West Virginia?
The rate the State Tax Commissioner sets under § 11-10-17a: the adjusted prime rate plus three percentage points, fixed each year and effective January 1. Check the current year's rate with the State Tax Department.
Does West Virginia cap retainage?
The code sections reviewed for this page set no retainage cap for public or private work, and a Levelset guide states the state has no retainage statute. The contract sets the rate and release terms.
Does West Virginia have a prompt payment law for private construction?
No private construction prompt pay statute was found. Payment timing on private jobs is set by the contract, backed by lien rights.
How fast must a West Virginia general contractor pay subcontractors?
No statute sets a prime-to-sub deadline. Negotiate one in the subcontract, and on public work rely on the payment bond if the prime does not pay.
Sources
- West Virginia Code § 7-5-7, Prompt Pay Act of 1995 (counties)
- West Virginia Code § 8-13-22d, Prompt Pay Act of 1995 (municipalities)
- West Virginia Code § 11-10-17a, Determination of rate of interest
- West Virginia Code § 14-3-1, Interest when final payment is delayed
- West Virginia Code § 5-22-1, Bidding required; government construction contracts
- West Virginia Code § 5A-3-54, state agency prompt payment (section page and bill history)
- Levelset: West Virginia retainage requirements
- Husch Blackwell: West Virginia state-by-state summary of prompt payment (July 2020)
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.