Hawaii prompt payment act and retainage rules
On Hawaii state and county contracts, the agency pays within 30 days, the GC passes money to subs within 10 days, and retainage is capped at 5 percent with no new withholding after the job is half done. Private work is mostly governed by the contract.
Hawaii's prompt payment and retainage rules are in Chapter 103 of the Hawaii Revised Statutes and apply to public contracts with the State and the counties. Under HRS § 103-10, an agency must pay a proper statement within 30 calendar days, with interest at the prime rate plus 2 percent if it is late. Under § 103-10.5, the GC must pay subs within 10 days of receiving money, including retainage at final payment, and late payers owe a penalty of 1.5 percent per month in the retainage-release situations that section covers. Section 103-32.1 caps retainage at 5 percent and stops new withholding at 50 percent complete when progress is satisfactory. These sections do not cover private jobs.
| Rule | Requirement | HRS |
|---|---|---|
| Agency pays contractor | 30 calendar days after a proper statement or satisfactory performance, whichever is later | § 103-10(a) |
| Agency late interest | Prime rate (Wall Street Journal) plus 2%, per calendar quarter | § 103-10(a) |
| GC pays sub | 10 days after the GC receives the money, if the sub met its subcontract terms and no bona fide dispute exists | § 103-10.5(a) |
| Final payment to sub | Full payment, including retainage, 10 days after the GC receives final payment | § 103-10.5(b) |
| Retainage cap | 5% of amount due; no additional withholding after 50% complete if progress is satisfactory | § 103-32.1(c) |
| Sub retainage | No higher percentage than the GC's when the sub provides a bond or acceptable collateral; subcontracts may set up to 10% of each progress payment, reflecting the sub's ability to bond | § 103-32.1(d), (e) |
| Late retainage penalty | 1.5% per month on amounts not timely paid by the procurement officer or GC | § 103-10.5(c) |
| Substitution | General obligation bonds of the State or a county may replace retainage | § 103-32.2 |
How the 30-day agency payment rule works
Section 103-10 is Hawaii's general prompt payment act for government purchases, and it covers construction along with other goods and services. Payment is due no later than 30 calendar days after the agency receives a proper statement or the work is satisfactorily performed, whichever is later. If the agency misses that date, interest runs from the 30th day to the date of the check at the prime rate plus 2 percent. The prime rate is the one posted in the Wall Street Journal on the first business day of the month before each calendar quarter.
- No interest for certain delays: a bona fide dispute, a labor dispute, a power or mechanical failure, fire, acts of God, or similar circumstances beyond the government's control.
- Federal money: if the bid solicitation clearly says payment depends on federal funds or approval, interest does not start until 30 days after the later of the contractor's statement or receipt of the federal funds or approval.
Flow-down to subcontractors
Under § 103-10.5, money paid to the GC must reach each sub within 10 days of receipt, as long as the sub has met its subcontract terms and there is no bona fide dispute on which the procurement officer has withheld payment. At final payment, the GC must pay the sub in full, including retainage, within 10 days of receiving the money unless there is a bona fide dispute over the sub's performance. A GC that violates the final-payment rule three or more times within two years is referred by the procurement officer to the contractors license board.
Early release of a sub's retainage
Hawaii has a specific path for subs who finish early. Once a sub has shown it completed all its work and submitted a properly documented final payment request, the money held for it must be paid through the GC if either of two things is true. One: the sub provided an acceptable performance and payment bond. Two: 90 days have passed since the sub's last labor or material with no written notice of a claim to the contractor and surety, and the sub provided a release of retainage bond (for no more than twice the amount held), another acceptable bond, or other agreed collateral. If the procurement officer or the GC fails to pay on time, a penalty of 1.5 percent per month applies, and the penalty can come out of the GC's future payments if the GC caused the delay.
The final payment request must substantiate the amounts and include a certification that the sub has paid its own subs and suppliers from earlier payments and will pay them from this one. The procurement officer has 7 days to return a defective request to the GC with a statement of the defect.
Retainage limits on public contracts
Section 103-32.1 says the procurement officer holds all retainage. It may not exceed 5 percent of the total amount due the contractor, and once the contract is 50 percent complete with satisfactory progress, no more is withheld. If progress is not satisfactory, the officer may keep withholding up to 5 percent. Liquidated damages are not counted as retainage. Contractors can swap retainage for State or county general obligation bonds under § 103-32.2. A dispute between a GC and a sub does not make the State or county a party.
Down the chain, a GC may hold no higher percentage from a sub than the State holds from the GC if the sub provides a performance and payment bond, another acceptable bond, or acceptable collateral. Separately, the parties may negotiate a retention of up to 10 percent of each progress payment, without late-payment interest, with the percentage reflecting the sub's ability to furnish bonds and still subject to that bond rule. A GC may also withhold part of a sub's pay request without interest or penalty, if the procurement officer determines the amount may be withheld, by giving the sub written notice, copied to the procurement officer, stating the amount, the specific cause under the subcontract, and what the sub must do to get paid.
Private work and pay-if-paid
The Chapter 103 rules above apply to public contracts. They do not set payment deadlines, interest, or a retainage cap for private construction, so on private jobs those terms come from the contract. Hawaii's statutes reviewed here also do not address pay-if-paid clauses, so enforceability turns on contract wording and case law. Have an attorney review the subcontract and keep Hawaii mechanics lien deadlines on the calendar.
The early-release path only works if someone tracks the 90-day window and the paperwork. Smart Business Automator logs last work dates, bonds, and retainage held per sub. See construction accounts receivable automation, and check Hawaii prevailing wage rules for the same public jobs.
Frequently asked questions
What is the retainage limit on Hawaii public contracts?
5 percent of the amount due the contractor under HRS § 103-32.1, with no additional withholding after the contract is 50 percent complete if progress is satisfactory.
How fast must a Hawaii GC pay subcontractors on public work?
Within 10 days after receiving the money, if the sub has met its subcontract terms and there is no bona fide dispute. At final payment, retainage is also due within 10 days.
What interest does a Hawaii agency owe on late payments?
The prime rate as posted in the Wall Street Journal plus 2 percent, starting on the 30th day after a proper statement or satisfactory performance, whichever is later.
Can a Hawaii subcontractor hold 10 percent from its sub-tier?
A subcontract may set retention of up to 10 percent of each progress payment, with the percentage reflecting the lower tier's ability to furnish bonds. If the lower tier provides a bond or acceptable collateral, the percentage cannot exceed what is held from the upper tier.
Does Hawaii have a private prompt payment law?
The Chapter 103 prompt payment and retainage sections cover public contracts only. On private jobs, the contract sets payment timing and retainage.
Sources
- FindLaw (current as of January 1, 2025): HRS § 103-10, Payment for goods and services
- Hawaii State Legislature: HRS § 103-10.5, Prompt payment (archive.org copy, February 2025)
- FindLaw (current as of January 1, 2025): HRS § 103-32.1, Contract provision for retainage; subcontractors
- Hawaii State Legislature: HRS § 103-32.2, Substitution of retainage (archive.org copy, August 2026)
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.