Arizona prompt payment act and retainage rules
Arizona's private Prompt Pay Act (A.R.S. 32-1181 to 32-1188) uses a certify-then-pay system: a billing is deemed approved after 14 days unless the owner objects in writing, then payment is due in 7. Public work under A.R.S. 34-221 has its own 7 and 14 day clock and a 10 percent retention rule.
In Arizona, a private owner has 14 days to object in writing to a billing; if it does not, the billing is deemed certified and approved and payment is due 7 days later. Subs must be paid within 7 days after the contractor receives payment, and late money earns 1.5 percent per month. On public work governed by A.R.S. 34-221, a pay estimate is deemed approved after 7 days and paid within 14, the owner retains 10 percent (halved at 50 percent complete if progress is satisfactory), and late payments earn 1 percent per month.
| Rule | Private work (A.R.S. 32-1181 to 32-1188) | Public work (A.R.S. 34-221) |
|---|---|---|
| Billing approval | Deemed certified and approved 14 days after receipt unless the owner issues a written statement of reasons | Deemed approved 7 days after submission unless a specific written finding is issued |
| Owner to prime | 7 days after certification and approval (contract can extend with required plan-sheet legend) | 14 days after the estimate is certified and approved |
| Prime to sub | 7 days after receipt of each progress payment, retention release, or final payment | 7 days after receipt of each progress payment, unless otherwise agreed in writing |
| Interest | 1.5 percent per month, or a higher agreed rate | 1 percent per month |
| Retainage | "Reasonable amount"; GC may not hold more from a sub than the owner holds for that sub's work | 10 percent; half released at 50 percent complete on request and no more than 5 percent after, if progress is satisfactory |
| Retainage release | Billing at substantial completion, deemed approved in 14 days, paid 7 days later | Within 60 days after completion or filing notice of completion |
| Substitute security | Not addressed in the act | Yes, at the contractor's option; subs get the same option if the prime uses it |
Private projects: how the Prompt Pay Act clock works
The act applies to construction contracts between owners and contractors and down the chain. Billings run on a 30 day cycle unless the contract and every page of the plans carry a clear legend setting a different cycle. A billing is deemed certified and approved 14 days after the owner (or the person the owner designates) receives it, unless before then the owner issues a written statement giving its reasons in reasonable detail. Once approved, payment is due within 7 days.
An owner can only decline to certify for the reasons the statute lists, such as unsatisfactory progress, defective work not remedied, disputed work, third-party claims, or failure to pay subs. It can only withhold enough to cover the direct costs it reasonably expects to incur. Owners can stretch the approval or payment periods, but only by putting the exact statutory legend ("Notice of Extended Payment Provision" or "Notice of Extended Certification and Approval Period Provision") in clear type on each page of the plans. That is where your estimator should look during bid review.
- Sub payments: the contractor pays each sub the full amount received for that sub's work within 7 days of receiving a progress payment, retention release, or final payment. Interest starts on the eighth day at 1.5 percent per month.
- Withholding from a sub: allowed for listed reasons, but the contractor must give a written statement within 14 days explaining why.
- Owner rejects for someone else's defect: if the owner short-pays because of one trade's defective work, the contractor must still pay the subs whose work was not the problem within 21 days after payment would otherwise have been made.
- Payment notice: a sub can ask the owner in writing to be notified within 5 days after each progress payment, retention release, or final payment to the contractor.
- Suspension: a contractor can suspend or terminate for nonpayment of certified amounts after 7 calendar days' written notice, and a clause waiving that right is void under A.R.S. 32-1186.
Section 32-1182(P) says a construction contract shall not alter the rights of any contractor, subcontractor, or supplier to receive prompt and timely payment under the article. That language is worth knowing when a subcontract includes a pay-if-paid clause, although the statute does not spell out how a court would apply it to one. Owner-occupant homes are covered only if the contractor puts the statutory notice from A.R.S. 32-1188 on the front page of each billing.
Private retention
The private act lets the owner withhold "a reasonable amount for retention" without a fixed percentage. The hard rule is downstream: a contractor or sub may not withhold retention from a sub in an amount greater than what the owner actually retains for that sub's work. At substantial completion the contractor submits a billing for release of retention. It is deemed approved in 14 days unless the owner objects, and the owner can hold back no more than 150 percent of the direct cost to finish incomplete items. Payment follows within 7 days. Owners may define retention and completion differently only with the "Notice of Alternate Arrangements" legend on the plans.
Public projects under A.R.S. 34-221
Public contracts awarded to the lowest responsible bidder under A.R.S. 34-221 must include monthly progress payments on jobs of 90 days or more. An estimate is deemed approved and certified 7 days after submission unless the owner issues a specific written finding of the items not approved, and the payment is due within 14 days after approval. The owner retains 10 percent of each estimate. At 50 percent complete, if progress is satisfactory, half the retained amount is paid on the contractor's request and no more than 5 percent is held from later payments, though the owner can reinstate 10 percent if progress slips.
Retention is paid within 60 days after completion or filing of the notice of completion. Holding it longer than 60 days after final completion and acceptance requires a specific written finding. In place of cash retention, the contractor can assign approved accounts, certificates of deposit, or government securities and keep the interest; if the prime does, its subs may do the same. Primes pay subs within 7 days of each progress payment, late payments to the prime earn 1 percent per month, and sub payments late by more than 7 days earn 1 percent per month from the eighth day.
Related Arizona guides
See Arizona mechanics lien law for lien and notice deadlines, Arizona contractor license requirements for the registrar of contractors (which can discipline a contractor who diverts sub payments), and Arizona prevailing wage. For the general concepts, see retainage and the prompt payment act. Tracking 14 day approval windows across jobs is a natural fit for construction accounts receivable automation in Smart Business Automator.
Frequently asked questions
How long does an Arizona owner have to approve a pay application?
On private work under A.R.S. 32-1182, a billing is deemed certified and approved 14 days after receipt unless the owner issues a written statement of reasons. On public work under A.R.S. 34-221, an estimate is deemed approved 7 days after submission unless a written finding is issued.
What interest applies to late construction payments in Arizona?
1.5 percent per month on private work (or a higher agreed rate) and 1 percent per month on public work under A.R.S. 34-221.
What is the retainage rate on Arizona public projects?
A.R.S. 34-221 has the owner retain 10 percent. At 50 percent complete with satisfactory progress, half is released on request and no more than 5 percent is held from later payments. Retention is paid within 60 days after completion.
Can an Arizona GC hold more retainage from a sub than the owner holds?
No. On private work, A.R.S. 32-1183 bars withholding retention from a sub greater than the amount the owner actually retains for that sub's work. Public work limits it to the percentage the owner retains.
Can an owner extend Arizona's payment deadlines?
Yes, on private work, but only if the contract says so clearly and the statutory notice legend appears on each page of the plans, including bid plans.
Sources
- Arizona Legislature: A.R.S. 32-1181, definitions; applicability
- Arizona Legislature: A.R.S. 32-1182, progress payments by owner; conditions; interest
- Arizona Legislature: A.R.S. 32-1183, performance and payment by contractor, subcontractor or material supplier
- Arizona Legislature: A.R.S. 32-1185 and 32-1186, suspension, termination, and void provisions
- Arizona Legislature: A.R.S. 32-1188, dwellings for owner-occupants
- Arizona Legislature: A.R.S. 34-221, payments to contractor; security; progress payments
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.