How to fill out AIA G702 and G703
Fill out the G703 continuation sheet first, one schedule of values line at a time, then carry its totals to the G702 summary page, apply retainage, subtract what you were already certified, and sign.
To fill out an AIA pay application, start with the G703 continuation sheet. List every line of your approved schedule of values, enter what was billed before, what you installed this period, and what material is stored, then total the columns. Those totals go onto the AIA G702 summary page, where you add change orders, take out retainage, subtract prior certificates, and arrive at the current payment due. The contractor signs (and notarizes if the contract asks for it), and the architect certifies the amount.
The order matters. AIA's own instructions say the summary information from the G703 is transferred to the G702 after the G703 is complete. People who start on the G702 and back into the detail are the ones who end up with a line 4 that does not match anything.
What the G702 and G703 are
The G702 is the Application and Certificate for Payment. It is one page: the contractor's request on the left, the architect's certificate on the right. The AIA G703 is the Continuation Sheet, the detail behind the request. AIA describes the pair as made for projects where the contractor has a direct agreement with the owner, with the procedures set out in the A201 general conditions. AIA does not publish a separate schedule of values form, so the G703 usually carries the SOV itself.
Step by step: filling out the G703
- Columns A, B, and C. Enter the item number, description, and scheduled value for each line, straight from the schedule of values approved at the start of the job (or as adjusted). Keep the same breakdown every month. Column C should start out equal to the original contract sum.
- Column D, from previous application. Copy what the last pay app showed in its columns D and E for each line. Do not carry over last month's stored materials here.
- Column E, this period. Enter the value of work put in place since the last application. If material that was stored last month got installed this month, its value moves into E now.
- Column F, materials presently stored. Enter the value of material stored and not yet installed, both new deliveries and older stored material still sitting on site or in an approved warehouse. Recalculate this total every period.
- Column G, total completed and stored. Add D, E, and F. Divide G by C for percent complete.
- Column H, balance to finish. Subtract G from C.
- Column I, retainage. Use it only if your contract allows retainage to vary by line. If one flat rate applies to the whole contract, leave it blank and calculate retainage on the G702.
- Subtotal and total. Subtotal column C at the bottom of each page except the last, and total it on the last page. Add up D through I the same way.
Step by step: filling out the G702
With the G703 totaled, the G702 is mostly arithmetic. The line labels below are the ones printed on the form.
| Line | Label | Where the number comes from |
|---|---|---|
| 1 | Original contract sum | The signed contract. It never changes. |
| 2 | Net change by change orders | The change order summary box (approved changes only) |
| 3 | Contract sum to date | Line 1 plus line 2 |
| 4 | Total completed and stored to date | Column G total from the G703 |
| 5 | Retainage | Retainage on completed work plus retainage on stored material |
| 6 | Total earned less retainage | Line 4 minus line 5 |
| 7 | Less previous certificates for payment | Line 6 from last month's certified application |
| 8 | Current payment due | Line 6 minus line 7 |
| 9 | Balance to finish, including retainage | Line 3 minus line 6 |
The change order summary
The box at the lower left splits approved change orders into those approved in previous months and those approved this month, additions and deductions in separate columns. The net of that box is line 2. Pending change order requests do not go here. Bill them only after they are signed.
Signature, notary, and the architect's certificate
AIA's instructions say the contractor signs the G702, has it notarized, and submits it with the G703 to the architect. Sign in your actual capacity (president, partner, and so on). The architect reviews both pages and, if acceptable, completes the certificate. The architect can certify a different amount than you asked for, and when that happens AIA says the architect initials every changed figure on both forms and attaches an explanation. The owner then pays the certified amount.
Worked example: month three on a tenant improvement
Here is an illustration. Say a general contractor has a $480,000 tenant improvement with 10 percent retainage, plus one approved change order last month for $12,000 of added data cabling. Prior certified payments total $153,000 (line 6 of the month two pay app).
| Item | Amount |
|---|---|
| Line 1, original contract sum | $480,000 |
| Line 2, net change by change orders | $12,000 |
| Line 3, contract sum to date | $492,000 |
| G703 column D (previous applications) | $170,000 |
| G703 column E (this period) | $95,000 |
| G703 column F (stored: light fixtures in the space) | $18,000 |
| Line 4, total completed and stored (column G) | $283,000 |
| Line 5, retainage at 10 percent | $28,300 |
| Line 6, total earned less retainage | $254,700 |
| Line 7, less previous certificates | $153,000 |
| Line 8, current payment due | $101,700 |
| Line 9, balance to finish including retainage | $237,300 |
Check the math the way the reviewer will. Line 4 must equal the G703 column G total. Line 9 must equal line 3 minus line 6. Line 7 must match last month's line 6 as certified, not as you submitted it. If the architect cut month two by $4,000, your line 7 is the lower number.
Mistakes that get pay apps sent back
- Line 4 does not tie to column G. Usually caused by a hand-typed G702 or a hidden spreadsheet row.
- Billing unapproved changes. Pending pricing slips into line 2 or into a base line. Reviewers catch it and hold the whole application.
- Stored material without backup. Many contracts require invoices, photos, insurance, or a bill of sale before stored material is paid. See how to bill stored materials.
- Front-loading. Percent complete on early lines that runs well ahead of the field. Superintendents and lenders walk the job, and an obvious mismatch costs trust on every later pay app.
- Using last month's submitted numbers instead of certified numbers for column D and line 7.
- Missing attachments. Lien waivers, certified payroll on public jobs, and updated schedules are often required with each application. A perfect G702 still sits if the package is incomplete.
Templates, terms, and tools that help
Build your line items once with the schedule of values template and see how to build a schedule of values before the first billing. Track what is held back with the retainage tracking template, and read how to bill retainage correctly for the release invoice. Related terms: pay application, progress billing, and stored materials.
Smart Business Automator builds the continuation sheet from your schedule of values and approved change orders, carries certified amounts forward each month, and calculates retainage, so the G702 lines tie out before anyone signs. See construction accounts receivable automation.
Frequently asked questions
Does the AIA G702 have to be notarized?
AIA's instructions say the contractor should sign the G702 and have it notarized. Some owners waive the notary in the contract, and some require it. Follow the contract and the owner's billing instructions for your job.
What goes in column I on the G703?
Column I is for retainage when the contract allows different rates on different lines. If one flat percentage applies to the whole contract, AIA says the column does not need to be filled in, and retainage is calculated on line 5 of the G702.
Can a subcontractor use the G702 and G703?
Many general contractors ask subs to bill on G702 and G703 or a look-alike form so they can roll the numbers into their own pay app. AIA designed the pair for contractors with a direct agreement with the owner, so read your subcontract for the required format.
What if the architect changes my numbers?
The architect may certify a different amount and must initial the changed figures and attach an explanation. Use the certified figures as your starting point next month, and resolve the difference through the contract's dispute or change process.
Where do pending change orders go?
Nowhere on the pay app until they are approved. The change order summary and line 2 include approved changes only. Track pending requests separately and push for signatures before the billing cutoff.