What is the AIA G702 form?

AIA G702 is the Application and Certificate for Payment: the summary page of a monthly pay app where the contractor requests payment and the architect certifies how much is due. The contractor prepares and signs it, and the architect may certify a different amount. The line-by-line detail behind its totals lives on the AIA G703 continuation sheet.

Two construction professionals review paper plans beside a tablet at a jobsite workbench.
Plan reviews connect field conditions, drawings, and the next decisions on a job. AI-generated illustration.

The AIA G702, Application and Certificate for Payment, is the cover page of a construction pay application. It serves two purposes on one sheet. The contractor uses it to request payment, and the architect signs it to certify to the owner that a stated amount is due. The detail behind the totals lives on the AIA G703 continuation sheet, and the two are always used together.

AIA designed the 1992 edition for jobs where the contractor has a direct agreement with the owner. Subs billing a GC often use a G702 look-alike, and AIA publishes separate versions for other delivery methods, such as cost of the work and construction manager as adviser contracts.

The lines on a G702

The G702 walks from the contract sum to the check amount in a fixed order. Each line pulls from the line above it or from the G703 totals.

G702 summary lines
LineWhat it shows
1. Original contract sumThe signed contract amount
2. Net change by change ordersApproved additive and deductive changes
3. Contract sum to dateLine 1 plus line 2
4. Total completed and stored to dateColumn G total from the G703
5. RetainageWithheld on completed work and on stored material
6. Total earned less retainageLine 4 minus line 5
7. Less previous certificates for paymentWhat was certified on earlier pay apps
8. Current payment dueLine 6 minus line 7
9. Balance to finish, including retainageLine 3 minus line 6

Below the lines sits a change order summary, the contractor's signature, and the architect's certificate. Many versions in use also carry a notary block, and some owners and lenders insist on a notarized signature every month, so leave time for that.

Example: filling out a G702

Take a $1,400,000 school renovation with $62,000 of approved change orders, so the contract sum to date is $1,462,000. The G703 shows $640,000 completed and stored to date. Retainage is 5 percent, or $32,000, leaving $608,000 earned less retainage. Previous certificates total $475,000. Line 8, current payment due, is $133,000. Line 9 shows $854,000 left to finish, including the retainage still held.

If the architect disagrees with the drywall percentage and cuts $9,000 of completed work, the certified amount becomes $124,450 after retainage. The architect is supposed to explain any change in the certification, and the contractor should initial the revised figures on its copy.

Common G702 problems

  • Line 7 pulled from previous requests instead of previous certificates. If last month was cut, this month will not tie.
  • Change orders listed in the summary that are still unsigned. Only executed changes belong on line 2.
  • Retainage calculated at the wrong rate after a contract reduction (for example, a drop from 10 to 5 percent at 50 percent complete).
  • Signature or notary missing, which often means the pay app waits a full cycle.
  • Using an old or unlicensed copy when the contract requires the official current document.

Related terms

The G702 is the heart of AIA billing and the most common pay application format. It reports retainage, stored materials, and the contract sum. For a step-by-step version, see how to fill out AIA G702 and G703.

Frequently asked questions

Who fills out the G702?

The contractor prepares and signs it. The architect, or whoever the contract names to review payment, completes the certificate section and may certify a different amount.

Does a G702 need to be notarized?

It depends on the contract and the owner. Many owners and lenders require notarization; others accept a plain signature. Read the payment section of the contract.

Can a subcontractor use a G702?

Yes. Many GCs ask subs to bill on a G702 and G703 format. The 1992 edition is written for an owner and contractor relationship, so subs often use a modified version or the GC's own form.

What is the difference between G702 and G703?

The G702 is the one-page summary and certificate. The G703 is the line-by-line detail by schedule of values item that produces the totals on the G702.

Sources

  1. AIA Contract Documents: Summary of G702-1992, Application and Certificate for Payment
Written and edited by

Maurice Francois writes and edits construction operations guides for Smart Business Automator. More from Maurice on the Scaling Legends podcast.