What is a sealed bid in construction?
A sealed bid is a firm price submitted in confidence by a deadline, then opened publicly at a stated time and place, with the contract going to the lowest bid that meets the requirements from a qualified bidder. Federal agencies use it under FAR Part 14. Unlike an RFP, there is no negotiation, and prices cannot change after opening.
Sealed bidding is the classic way public owners buy construction. Every bidder prices the same documents, nobody sees anyone else's number before opening, and the price decides the award. Federal agencies use it under FAR Part 14, and most state, county, and city public works laws require something similar for projects over a dollar threshold set in local law. Private owners sometimes use the same format to keep a bid day clean.
How sealed bidding works
FAR 14.101 lays out the steps for federal work, and most public owners follow the same shape:
- The invitation. The owner issues an invitation to bid that must describe its requirements clearly, accurately, and completely.
- Publicizing. The invitation is distributed to prospective bidders and posted publicly, often with a pre-bid meeting.
- Submission. Bidders submit sealed bids to be opened at the time and place stated in the solicitation. Late bids are handled under strict separate rules and are usually not considered.
- Evaluation. Bids are evaluated without discussions. Bidders cannot negotiate or revise after opening.
- Award. After public opening, award goes with reasonable promptness to the responsible bidder whose conforming bid is most advantageous, judged only on price and the price-related factors in the invitation.
The no-discussions rule is the heart of it. Unlike a negotiated request for proposal, you cannot sharpen your number after you see the competition.
A bid day example
A water district advertises a $1.2 million lift station replacement with bids due Thursday at 2:00 p.m. A mechanical contractor's estimator has subs and suppliers calling in prices until 1:30. At 1:45 the bid form is signed, the bid bond attached, and all four addenda acknowledged. A runner hands it in at 1:52. At 2:00 the district reads every bid aloud and posts a bid tabulation.
The contractor is second, $18,000 above the low bid. Two weeks later, the low bidder is disqualified for a missing subcontractor listing form that the invitation required. The district checks the second bidder's responsibility and awards. Bid day discipline won the job, not price.
Common mistakes
- Arriving late or uploading late. Most agencies reject late bids, and "the elevator was slow" is not an exception.
- Adding qualifications or exclusions to a public bid form, which can make the bid nonresponsive.
- Missing an addendum acknowledgment or a required form in the envelope.
- Trying to withdraw after a math error. Mistake rules exist, but relief is narrow and needs clear evidence. Check the numbers before bid day ends.
- Assuming low price is final. The owner still reviews responsibility before award.
Related terms
See bid day, bid form, award, and design-bid-build, the delivery method that usually pairs with sealed bids. For the process end to end, read how to bid public construction projects. Smart Business Automator keeps bid documents, bonds, and forms organized per opportunity and per job; see public works contractor automation.
Frequently asked questions
Can you change a sealed bid after opening?
Generally no. Sealed bids are evaluated without discussions. Narrow rules allow correction or withdrawal for clear mistakes, but you cannot lower or raise your price because you saw other bids.
Does the lowest sealed bid always win?
Only if it is responsive to the invitation and the bidder is found responsible. Missing forms or an unqualified bidder can move the award to the next lowest bid.
Are sealed bids required on all public projects?
Not all. Public owners usually must use formal sealed bids above thresholds in their own laws or rules, and may use informal quotes or other methods for smaller jobs. Thresholds vary by jurisdiction.
What is the difference between a sealed bid and an RFP?
A sealed bid is awarded on price among responsive, responsible bidders without negotiation. An RFP lets the owner weigh price with other factors and negotiate with offerors.