What is a T&M contract in construction?

A T&M (time and materials) contract is an agreement where the owner pays agreed hourly rates for labor and pays for materials as used, instead of a fixed price for the whole scope. The owner carries the quantity risk, and the contractor carries the risk its rates are too low. Many include a not-to-exceed cap on the total.

A contractor and plan reviewer discuss drawings and permit paperwork across an office desk.
Keep plans, permit requirements and approvals together when preparing construction work. AI-generated illustration.

A T&M contract is a contract type, not just a billing method. It sets the rules for how a contractor gets paid when nobody can price the work up front: labor at fixed hourly rates by classification, materials at cost (often plus a markup), and equipment at agreed rates. The owner carries the quantity risk. The contractor carries the risk that its rates do not cover its true costs.

This page covers the contract itself: what the agreement should say and where the fights start. For the day-to-day tracking and invoicing side, see time and materials.

When a T&M contract makes sense

Federal rules give a useful test. FAR 16.601 says a time-and-materials contract may be used only when it is not possible at the time of placing the contract to estimate accurately the extent or duration of the work or to anticipate costs with any reasonable degree of confidence. It also requires a ceiling price that the contractor exceeds at its own risk, and notes that the contract type gives the contractor no positive profit incentive for cost control, so the owner must watch the work closely. Private owners are not bound by the FAR, but the same logic applies: emergency repairs, concealed-condition demolition, and service work are good fits. A defined tenant fit-out is not.

Clauses a T&M contract should spell out

What to put in writing
ClauseWhat it should say
Labor ratesHourly rate for each classification, and whether rates include burden, overhead, and profit
Overtime and premium timeWhen it applies and what multiplier is billed
MaterialsBilled at invoice cost, with or without a stated markup
EquipmentOwned and rented equipment rates, and minimum charges
Ceiling or not-to-exceedThe maximum the owner will pay without a written increase
DocumentationDaily signed tickets, receipts, and how fast they are submitted
Rate adjustmentsWhether rates escalate on a long contract

A worked example

Say a mechanical contractor signs a T&M agreement to trace and repair a failing hydronic loop in an occupied school over winter break, with a not-to-exceed of $85,000. Rates are $118 per hour for a journeyman fitter and $72 for a helper, fully burdened, with materials at cost plus 15 percent. In week one, a crew of two fitters and a helper works 40 hours each: 80 fitter hours at $118 is $9,440, plus 40 helper hours at $72 is $2,880, for $12,320 of labor. Valves and pipe come to $4,000 at cost, or $4,600 with markup. The week's bill is $16,920.

By week four the bills total $79,000 and the job is not done. The contract says the contractor must notify the owner before reaching the ceiling. The PM sends a written notice at $75,000 with a cost-to-complete estimate, and the owner issues a change raising the ceiling. Without that notice, the last few thousand dollars of work could have gone unpaid.

Common disputes

  1. Unsigned tickets. If the owner's rep did not sign the daily time ticket, the hours become negotiable.
  2. Rates that hide margin. Owners push back when "fully burdened" rates look high and no breakdown exists.
  3. Blowing through the ceiling. Work past a not-to-exceed without a written increase is often at the contractor's risk.
  4. Productivity arguments. Owners may challenge hours as excessive, especially with large crews or slow progress.

Related terms

T&M sits between the fixed-price contract and the cost-plus contract, and is often used for change orders when scope is unclear. Read time and materials contracts: when to use them before you sign one. Smart Business Automator records T&M tickets and approvals against the job so billing matches what the owner signed; see change order approval automation.

Frequently asked questions

What does T&M stand for in construction?

Time and materials. The contractor is paid for time worked at agreed hourly rates and for materials used, rather than a fixed price.

Is a T&M contract the same as cost-plus?

They are close cousins. Cost-plus reimburses actual costs and adds a fee. T&M pays preset hourly rates that already include overhead and profit, plus materials, so the contractor's real labor cost is not usually open to the owner.

What is a not-to-exceed amount?

A cap on the total the owner will pay under the T&M agreement. The contractor needs a written increase to be paid beyond it.

Who carries the risk in a T&M contract?

The owner carries most of the risk on quantity and duration. The contractor carries the risk that its rates are too low and that undocumented hours will be disputed.

Sources

  1. Acquisition.gov: FAR 16.601, Time-and-materials contracts