What is a partial lien waiver in construction?
A partial lien waiver releases a contractor's or supplier's lien rights only up to a specific progress payment or date. Rights for later work, retainage, and unpaid extras stay intact. It is also called a progress or interim lien waiver, and final payment gets a final waiver instead. Sign only a conditional version before the payment clears.
A partial lien waiver is the document a contractor, subcontractor, or supplier signs in exchange for a progress payment. It says, in effect: for the work through this date and this amount, I give up my right to file a mechanics lien. It is called partial because it does not cover the whole contract. The final payment gets a final lien waiver. Some people call it a progress waiver or an interim lien waiver.
Owners and lenders collect them every month so they know each dollar paid has cleared the lien risk for that work.
Conditional or unconditional
Partial waivers come in two flavors. A conditional lien waiver takes effect only when the payment actually clears. An unconditional lien waiver is effective the moment it is signed, paid or not. The safe habit: give conditional waivers with your pay application, and unconditional waivers only after the funds are in your account.
How state statutes treat them: Florida as an example
Several states publish statutory waiver forms. Florida's lien law, section 713.20, provides a form titled "Waiver and Release of Lien Upon Progress Payment" and a separate form for final payment. The statute says a right to claim a lien may not be waived in advance, and may be waived only for labor, services, or materials already furnished. It also allows waiving part of a lien, including amounts due through a specified date, and the progress form excludes retention and work performed after that date. A lienor may condition its waiver on a check clearing. Other states have their own forms and rules, and some require exact statutory language, so check the mechanics lien rules for your state.
How it works on a real job
Say a drywall sub has a $380,000 subcontract. Its April pay application is for $52,000 of work through April 30, less 10 percent retainage, so $46,800 is due. With the pay app it sends a conditional partial waiver for $46,800 through April 30. The GC is paid by the owner and pays the sub on May 28. After the check clears, the sub sends an unconditional partial waiver for the same amount and date.
The sub still holds lien rights for the $5,200 of April retainage, for May work, and for a disputed $9,000 change order it listed as an exception on the waiver.
Common mistakes
- Signing an unconditional waiver before getting paid. If the check never comes, the lien rights for that work may be gone.
- Leaving out exceptions. List disputed change orders, unpaid extras, and retainage on the waiver if the form allows it.
- Wrong through date. A through date later than the work billed can waive rights to work you have not been paid for.
- Signing the GC's custom form without reading it. Some custom forms add releases of claims beyond lien rights.
- Not tracking which waivers went out for which payments. A lien waiver tracking template fixes that.
Related terms
See lien waiver, lien release, progress payment, and the guide on conditional vs unconditional lien waivers.
Frequently asked questions
Does a partial lien waiver cover retainage?
Usually not. Most progress waivers cover only the amount paid, and Florida's statutory progress form expressly excludes retention. Read the form to confirm.
Should I sign a partial waiver before I am paid?
Only a conditional one. An unconditional waiver should wait until the payment has cleared your bank.
Do suppliers sign partial lien waivers?
Yes. Material suppliers with lien rights are usually asked for waivers too, especially on lender-financed jobs.
Can a partial waiver release future work?
It should not, and some states forbid it. Florida, for example, says lien rights may not be waived in advance and may be waived only for work already furnished.