What is a construction draw?
A construction draw is a scheduled release of money from a construction loan to pay for work that has been completed, usually after the lender's inspector confirms progress. The owner submits the draw request with the contractor's invoice or pay app. Inspection, title update, and approval commonly take one to two weeks, and lenders fund only verified work.
A construction draw is how lender money reaches the job. Instead of handing the borrower the whole construction loan at closing, the lender releases it in pieces as the building goes up. Each piece is a draw. The contractor bills, the owner requests the draw, the lender inspects, and funds are released, usually to the owner or a title company, which then pays the contractor.
Draws follow a draw schedule agreed at loan closing. On custom homes that schedule is often tied to milestones (foundation, framing, dry-in, rough-ins, drywall, trim, final). On commercial work, draws usually follow monthly pay applications against a schedule of values.
How the draw process works on a real job
Say a builder is putting up a $640,000 custom home with a bank loan. The draw schedule has seven milestones. Framing is the third, worth 18 percent of the contract.
- Framing and sheathing are done. The builder sends the owner an invoice for $115,200 (18 percent) with lien waivers from the framer and lumber yard.
- The owner submits the draw request to the lender with the invoice, waivers, and any change orders.
- The lender orders an inspection. The inspector visits, compares work in place to the budget, and reports percent complete by line.
- The inspector sees framing done but the roof sheathing only half on, and recommends 14 percent instead of 18.
- The lender releases $89,600 less retainage, if the loan holds any, often through a title company that updates its lien search first.
- The builder gets paid roughly 10 to 15 days after requesting, if nothing goes wrong.
The remaining 4 percent is not lost. It rolls into the next draw once the inspector sees the work. But the builder carried the framer's bill in the meantime.
Why draws get delayed
- Missing lien waivers from subs or suppliers.
- Change orders that were never sent to the lender, so the budget does not match the invoice.
- Billing ahead of the work. Lender inspectors are conservative and will cut the request.
- Stored materials that the loan does not fund until installed. See stored materials.
- Title updates that find a recorded lien or notice of commencement issue.
Draw versus progress payment
A progress payment is any payment for work completed so far. A draw is a progress payment funded from a loan, with the lender's inspection and paperwork rules layered on top. The contractor's contract is with the owner, not the lender, but in practice the lender's process sets the pace.
Related terms
See holdback, construction financing, progress billing, and lien waiver. The guide on how construction draws work with lenders and how to work with residential construction lenders go further. Smart Business Automator ties each draw invoice to its lien waivers so the package is complete when it goes out.
Frequently asked questions
Who requests a construction draw?
The borrower (usually the owner) submits the draw request to the lender, typically using the contractor's invoice or pay application as backup.
How long does a construction draw take?
It varies by lender. Inspection, title update, and approval commonly take one to two weeks. Missing paperwork is the usual cause of longer delays.
Do lenders pay the contractor directly?
Some do, through a title or escrow company. Others fund the borrower's account and the borrower pays the contractor.
Can a lender reduce a draw?
Yes. If the inspector finds less work in place than billed, the lender funds only what is verified, and the rest moves to a later draw.