What is a look-ahead schedule in construction?
A look-ahead schedule is a short-range plan, usually covering the next three to six weeks, that turns the master schedule into specific crew tasks and lists what must be ready before each one can start. The superintendent usually owns it, with input from foremen and the PM. Unlike the master schedule, it works at the task level.
A look-ahead schedule is the field's version of the project schedule. The master construction schedule might show one bar for "Level 2 MEP rough-in, 4 weeks." The look-ahead breaks that into what each trade does each day or week, in which area, and what has to be true first: submittals approved, material on site, inspection passed, the area handed over by the trade before.
The most common version is the three-week look-ahead, but horizons vary. Lean planning guidance from Lean Project Consulting, which works with the Lean Construction Institute's Last Planner System, describes a six-week make-ready plan. The point is the same either way: look far enough ahead to fix problems before crews hit them.
How a look-ahead works week to week
- Pull from the master schedule. Each week, the superintendent takes the activities due in the look-ahead window and breaks them into tasks a foreman can commit to.
- Screen for constraints. For each task, ask what could stop it: an open RFI, a submittal not returned, a long-lead item, a crane pick, an inspection, a trade behind. Each one goes on a constraint log with an owner and a need date.
- Clear or drop. Constraints get chased. If one cannot be cleared in time, the task comes off next week's plan instead of being started and stalled.
- Commit. Trade foremen commit to the tasks that are ready for the coming week.
- Measure. The next week, compare what was promised to what was done. Last Planner calls this percent plan complete (PPC), and the reasons for misses get logged and fixed.
Example: interior build-out, weeks 14 to 16
| Week | Task | Trade | Constraint | Status |
|---|---|---|---|---|
| 14 | Level 2 top-out framing, east wing | Framing | None | Ready |
| 14 | Level 2 in-wall plumbing rough | Plumbing | RFI 41 on sink locations | Answer due Tue |
| 15 | Level 2 above-ceiling inspection | GC | Sprinkler rough not complete | Sprinkler sub adding crew |
| 16 | Level 2 drywall hang, east wing | Drywall | Board delivery, needs hoist slot | Delivery booked Mon |
The plumbing row is the one that pays for the meeting. Without the look-ahead, the plumber shows up Monday with four guys and no answer on sink locations. With it, the PM has two days to get the architect to answer RFI 41, or the super moves the plumber to Level 3 and nobody stands around.
Common mistakes
- Copying the master schedule. A look-ahead with the same bars at the same level of detail adds nothing. It needs areas, crews, and constraints.
- Building it alone. If the super writes it without the trade foremen, the dates are wishes, not commitments.
- No constraint log. Listing tasks without what blocks them is just a calendar.
- Never measuring. If nobody checks what got done against what was promised, the plan gets less reliable each week and nobody knows why.
- Letting it drift from the master. When the look-ahead shows a slip, the master schedule and any critical path impact need updating too.
Related terms
See lean construction, baseline schedule, long-lead items, and submittal schedule. The guide how to make a three-week look-ahead schedule walks through building one, and the three-week look-ahead template gives a starting layout. Smart Business Automator links open RFIs and submittals to project tasks, which helps surface constraints before the look-ahead meeting; see RFI and submittal tracking automation.
Frequently asked questions
How far ahead should a look-ahead schedule go?
Three weeks is common for the detailed version. Lean teams using the Last Planner System often screen work six weeks out so long constraints like submittals and deliveries can be cleared in time.
Who owns the look-ahead schedule?
Usually the superintendent, built with input from trade foremen and the project manager. The PM typically chases the paperwork constraints, and the super handles field sequencing.
How is a look-ahead different from the master schedule?
The master schedule covers the whole job at the activity level and is often contractual. The look-ahead covers a few weeks at the task level and exists to make the work ready.
What is percent plan complete?
It is the share of tasks committed for a week that were actually finished. It is a Last Planner System measure of how reliable the plan is, not a measure of overall project progress.