What is a claim in construction?
A construction claim is a formal written demand by one party, usually the contractor, for additional money, time, or another contract adjustment that the other party has not agreed to. A change order is an agreed change; a claim goes through the contract's dispute process. Notice windows are often short, and federal claims over $100,000 must be certified.
In construction, a claim is what a change request becomes when the parties cannot agree. The contractor says the owner owes more money or more days. The owner says no. The claim is the formal, contract-defined process for asserting that right and getting a decision, first from whoever the contract names (often the architect or an initial decision maker) and then, if needed, through mediation, arbitration, or court.
Owners can file claims too, for example for defective work or delay damages. But most claims come from contractors and subcontractors, and they come in a few familiar types.
Common types of construction claims
- Delay claims: time and extended costs from owner-caused delay. See delay claim.
- Differing site conditions: rock, groundwater, or hidden conditions that differ from the contract documents. See differing site conditions.
- Disputed changes: work the contractor says was extra and the owner says was in scope.
- Acceleration: being forced to speed up without a time extension.
- Payment: unpaid contract balance or retainage.
How a claim works on a real job
Say a site contractor on a $2.7 million parking lot hits unmapped rock across 30 percent of the excavation. The contract has a differing site conditions clause and a short notice window. The contractor stops work in that area, notifies the owner in writing the same week, photographs the rock, and records extra hours and equipment daily. The owner's engineer denies the request, saying the geotechnical report mentioned rock. The contractor files a formal claim for $186,000 and 18 days with its records and the report excerpts. The process from there follows the contract's dispute steps.
Notice is where most claims are won or lost. Standard forms set short deadlines to give written notice after the event or after the contractor first recognizes the condition. Miss the window and the owner will argue the claim is waived, regardless of merit.
Claims on federal contracts
Federal jobs follow the Contract Disputes Act. A contractor claim must be submitted in writing to the contracting officer within 6 years after the claim accrues. Claims over $100,000 must be certified: the contractor states the claim is made in good faith, the supporting data is accurate and complete, and the amount accurately reflects what it believes it is owed. For claims of $100,000 or less, the contracting officer must decide within 60 days of a written request. For certified claims over $100,000, the officer has 60 days to decide or say when a decision will issue.
Mistakes that sink claims
- Late or verbal notice.
- Global cost claims with no link between the event and the dollars.
- No daily records, photos, or daily logs tied to the event.
- Signing a change order or lien waiver that releases the claim without a reservation.
- Waiting until the end of the job to raise everything at once.
Related terms
See notice of claim, dispute resolution, no damages for delay clause, and change order request. The guide on how to document construction delays for claims covers the records.
Frequently asked questions
What is the difference between a claim and a change order?
A change order is an agreed change. A claim is a demand for an adjustment the other party has not agreed to, handled through the contract's dispute process.
How long do I have to give notice of a claim?
It depends on the contract, and the windows are often short. Read the notice clause at signing and calendar it.
Does a federal claim need to be certified?
Yes, if it is over $100,000. The Contract Disputes Act requires a certification of good faith and accurate supporting data signed by someone authorized to bind the contractor.
Can a subcontractor file a claim against the owner?
Usually not directly, because the sub has no contract with the owner. Subs often pass claims through the GC, sometimes under a liquidating or pass-through agreement.