Minnesota prompt payment act and retainage rules
Minnesota is one of the few states with matching public and private retainage rules: 5 percent maximum, released within 60 days after substantial completion. Primes pay subs within 10 days of being paid, and late money carries 1.5 percent a month.
Minnesota's prompt payment act rules come in matched pairs. On public jobs, Minn. Stat. § 15.72 caps retainage at 5 percent and requires release within 60 days after substantial completion. On private jobs, § 337.10, subd. 4 says the same thing. Owners pay on their own clocks: State agencies within 30 days of an invoice (§ 16A.124), cities and counties within 35 days when the board meets monthly (§ 471.425). Down the chain, primes and subs must pay within 10 days of receiving payment for undisputed work, with interest at 1 1/2 percent per month on late amounts.
| Rule | State agencies | Cities, counties, other municipalities | Private work |
|---|---|---|---|
| Owner pays prime | Within 30 days after invoice receipt (§ 16A.124, subd. 3) | Per contract, or within 35 days of receipt if the board meets monthly; 45 days if not (§ 471.425, subd. 2) | Monthly as work progresses unless the contract says otherwise (§ 337.10, subd. 4) |
| Late owner interest | 1 1/2% per month, $10 minimum on $100 or more (§ 16A.124, subd. 5) | 1 1/2% per month, $10 minimum on $100 or more (§ 471.425, subd. 4) | Not set by statute for the owner |
| Prime pays subs | Within 10 days of receipt (§ 337.10, subd. 3) | Within 10 days of receipt; required contract term (§ 471.425, subd. 4a) | Within 10 days of receipt (§ 337.10, subd. 3) |
| Late sub interest | 1 1/2% per month, $10 minimum | 1 1/2% per month, $10 minimum | 1 1/2% per month, $10 minimum |
| Retainage cap | 5% of each payment (§ 15.72, subd. 2) | 5% of each payment (§ 15.72, subd. 2) | 5% (§ 337.10, subd. 4) |
| Retainage release | Within 60 days after substantial completion | Within 60 days after substantial completion | Within 60 days after substantial completion |
When public owners must pay
State agencies must pay a valid obligation within 30 days after receiving the invoice for completed delivery, under § 16A.124. On construction, partial payments count as invoices when submitted at regular intervals of at least monthly, as the contract specifies. Interest accrues at 1 1/2 percent per month or any part of a month on undisputed bills unpaid after 30 days, with a $10 monthly minimum on balances of $100 or more. One catch: § 16A.124, subd. 5 says no interest accrues on contractor claims under a construction contract, so a disputed change order claim is a different fight.
Municipalities follow § 471.425. Without contract terms, a board that meets at least monthly pays within 35 days of the date of receipt, and one that does not pays within 45 days. If an invoice is wrong, the municipality has 10 days to say so, and the clock restarts with the corrected invoice. Late interest is 1 1/2 percent per month, with the same $10 minimum, unless the municipality disputes the bill in good faith.
Paying subs within 10 days
Section 337.10, subd. 3 requires primes and subs to pay their subs and suppliers within 10 days of receiving payment for undisputed services. Late undisputed amounts earn 1 1/2 percent per month, with a $10 monthly minimum on balances of $100 or more. A sub that wins a lawsuit to collect those interest penalties must be awarded costs and attorney fees, and an unpaid party may suspend work if an undisputed payment is not received within 10 days. Every municipal contract must carry the same 10-day requirement under § 471.425, subd. 4a.
Example: a mechanical sub is owed $62,000 on a county library job, and the GC was paid on the 5th. The money is due by the 15th. If it is paid on the 20th, the interest for that part of a month is 1 1/2 percent, or $930. That is real money, and it is why GCs track the date each owner check lands.
Retainage on public and private work
- Cap: 5 percent, which the owner may reduce or eliminate if the work is going well (§ 15.72, subd. 2; § 337.10, subd. 4).
- Release: all retainage within 60 days after substantial completion.
- Holdbacks after completion: the owner may keep 250 percent of the cost to correct or complete work known at substantial completion, and the greater of 1 percent of the contract or $500 pending final paperwork. Each is paid within 60 days after the work is done or the paperwork is submitted.
- No warranty retainage: holding retainage for warranty work is prohibited.
- Flow-down: the prime pays sub retainage within 10 days after receiving its own, and when the owner reduces retainage, the prime must reduce sub retainage at the same rate (§ 15.72, subd. 2; § 337.10, subd. 4).
- Scope: the private rule in § 337.10, subd. 4 does not apply to public agencies or professional services contracts.
On public jobs paid with state or federal aid, the agency does not have to pay that portion until the aid arrives. On streets, highways, and bridges, § 15.72 defines substantial completion as the point when construction traffic devices and ongoing inspections are no longer needed. Neither statute addresses pay-if-paid clauses by name, but § 337.10, subd. 2 voids terms that require a lien or bond claim waiver before payment, and subd. 1 voids clauses putting Minnesota work under another state's law.
Smart Business Automator tracks the receipt date of each owner payment and the 10-day sub deadline on every job. See construction accounts receivable automation.
Frequently asked questions
What is the retainage limit in Minnesota?
Five percent, on both public work (§ 15.72) and private work (§ 337.10, subd. 4). Retainage must be released within 60 days after substantial completion.
How fast must a Minnesota prime contractor pay subcontractors?
Within 10 days of receiving payment for undisputed work, under § 337.10, subd. 3. Late amounts carry 1 1/2 percent per month, with a $10 monthly minimum on balances of $100 or more.
How long does a Minnesota city have to pay a contractor?
Under § 471.425, the contract controls. Without contract terms, a board that meets at least monthly pays within 35 days of receipt, and one that does not pays within 45 days.
Can a Minnesota owner hold retainage for warranty work?
No. Both § 15.72 and § 337.10, subd. 4 prohibit withholding retainage for warranty work.
Can a Minnesota sub stop work for nonpayment?
Section 337.10, subd. 3 lets an unpaid party suspend work if an undisputed payment is not received within 10 days.
Sources
- Minnesota Revisor of Statutes: § 15.72, public construction contracts
- Minnesota Revisor of Statutes: § 16A.124, state prompt payment
- Minnesota Revisor of Statutes: § 471.425, prompt payment of local government bills
- Minnesota Revisor of Statutes: § 337.10, building and construction contracts
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.