Arkansas prompt payment act and retainage rules
Arkansas's clearest statutory payment rules for contractors are the public works retainage provisions in Ark. Code 22-9-601 to 22-9-604: a 5 percent holdback, an optional stop at 50 percent, and release within 30 days after completion.
On an Arkansas public works contract where the contractor furnishes a performance and payment bond, the contractor is entitled to 95 percent of earned progress payments when due, so the public agency holds 5 percent as retainage. The agency may stop withholding once the job is 50 percent complete and the work is satisfactory, and everything withheld must be paid within 30 days after the contract is completed. The parties cannot contract around these rules. Payment deadlines and interest for private jobs are mostly a matter of contract, so read yours closely.
| Rule | Public work | Private work |
|---|---|---|
| Retainage on bonded prime | 5 percent (contractor paid 95 percent of earned progress payments) | Set by the contract |
| Reduction | Agency may stop withholding at 50 percent complete if work is satisfactory and the design professional and agency agree | Set by the contract |
| Retainage release | Within 30 days after the construction contract is completed | Set by the contract |
| Phased occupancy | Partial release within 30 days, proportional to the completed portion, if the contract provides for phased work | Set by the contract |
| Prime to bonded sub | Same 95 and 5 percent structure; tied to the sub reaching 50 percent of its subcontract | Set by the subcontract |
| Stored materials | No retainage on stored materials or equipment the contract requires (on site or in a bonded warehouse) | Set by the contract |
| Waiver | Not allowed; parties cannot vary or waive the subchapter | Not applicable |
| Excluded | State Highway Commission highway, road, and street contracts | Not applicable |
Public works retainage under Ark. Code 22-9-604
The retainage subchapter covers public construction contracts where the contractor is required to furnish a performance and payment bond. The contractor gets 95 percent of each earned progress payment when due. The remaining 5 percent is security for faithful performance.
Retainage can stop at the halfway mark, but it is not automatic. The agency may forgo withholding once the construction contract is 50 percent complete, the contractor has performed satisfactorily, and both the design professional and the public agency agree. The agency can also choose to keep withholding through the whole project. That makes the 50 percent pay application a good moment to ask in writing, with a clean punch history and current lien waivers attached.
- Completion: all sums withheld are paid to the contractor within 30 days after the construction contract is completed.
- Phased projects: if the contract allows phased work with partial occupancy, retainage on the completed portion is released within 30 days, in proportion to that portion.
- Stored materials: when the contract requires the contractor to buy materials or equipment and store them on site or in a bonded warehouse for the job, no retainage is withheld on the part of the progress payment covering those items.
- No waiver: Ark. Code 22-9-603 says the parties have no authority to vary or waive the subchapter by agreement.
Consider a $1,600,000 county library job. Through the first half, the county holds 5 percent of each payment, about $40,000 by the time the job reaches $800,000 in earned value. If the architect and the county sign off at 50 percent, new progress payments can go out at 100 percent. The $40,000 already held then waits for completion, and the 30 day release clock starts when the contract is complete.
Retainage between the prime and its subs
Subsection (b) applies the same 95 and 5 percent structure between the prime and a subcontractor that furnishes a performance and payment bond, and it ties the reduction to the sub reaching 50 percent of its own subcontract with the prime's approval. Read the current text of subsection (b) and your subcontract together, because the trigger is the sub's progress, not the whole project's. Early-finishing trades like site work and foundations benefit most.
What the retainage statute does not cover
Ark. Code 22-9-602 excludes contracts the State Highway Commission enters into for building or maintaining public highways, roads, and streets, so ARDOT work follows its own specifications. Owner-to-prime progress payment deadlines and late payment interest are not set in the retainage subchapter. Check the agency's contract documents and general conditions for the payment period, and ask the procuring agency directly if the contract is silent.
On private projects, no Arkansas statute could be confirmed for this page that sets a prompt payment deadline or a retainage cap, so the contract controls the payment schedule, the retainage percentage, and the release trigger. That puts the weight on negotiation: ask for a fixed number of days after approval, a retainage step-down at 50 percent, and release tied to your own scope where possible. Watch any pay-if-paid clause closely, since without a statute it is the contract language that decides who carries the risk of owner nonpayment. Our guide to pay-if-paid vs pay-when-paid clauses walks through the differences.
Related Arkansas guides
See Arkansas contractor license requirements and Arkansas prevailing wage for the rest of the public bid picture, and the prompt payment act glossary entry for how these laws work in other states. Smart Business Automator keeps retainage by job and by sub so you know exactly what to bill when the 30 day release window opens; see construction accounts receivable automation.
Frequently asked questions
What is the retainage percentage on Arkansas public projects?
When the contractor furnishes a performance and payment bond, Ark. Code 22-9-604 entitles the contractor to 95 percent of earned progress payments, so the agency holds 5 percent.
When must Arkansas public retainage be released?
All sums withheld by the public agency are paid to the contractor within 30 days after the construction contract is completed. Phased projects with partial occupancy get proportional releases within 30 days.
Can an Arkansas public agency stop holding retainage at 50 percent?
It may, if the contract is 50 percent complete, the work is satisfactory, and the design professional and the agency agree. It is not required to.
Is retainage withheld on stored materials in Arkansas?
Not on public work under 22-9-604 when the contract requires the contractor to buy and store materials or equipment on site or in a bonded warehouse for the job.
Do the Arkansas retainage rules apply to highway work?
No. Ark. Code 22-9-602 excludes State Highway Commission contracts for constructing or maintaining public highways, roads, and streets.
Sources
- FindLaw (Arkansas Code text): Ark. Code 22-9-604, retainage procedure
- FindLaw (Arkansas Code text): Ark. Code 22-9-603, waiver of provisions prohibited
- FindLaw (Arkansas Code text): Ark. Code 22-9-602, State Highway Commission exclusion
Laws and rates change. Confirm current requirements with the state agency before you bid, file, or pay. This page is general information, not legal advice.