How to write bid clarifications and exclusions
Write each clarification or exclusion as one specific sentence tied to a drawing, spec section, or scope item, say who carries the excluded work if you know, and keep the list short enough that the reader actually reads it. On sealed public bids, skip them unless the instructions allow them.
Bid clarifications and exclusions tell the GC or owner exactly what your price covers. A good one is specific, references the documents, and is short. "Excludes firestopping at rated wall penetrations by other trades, spec section 07 84 00" is useful. "Excludes anything not specifically mentioned" is not, and a reviewer leveling bids will either ignore it or plug a big number against you. Write them as you read the plans, not at 1:45 p.m. on bid day, organize them into inclusions, exclusions, clarifications, and assumptions, and keep them in the same format on every bid so your clients learn to read them.
Inclusions, exclusions, clarifications, and assumptions
- Inclusions: items you are confirming are in your price, especially ones a reviewer might doubt ("Includes temporary power for our own tools").
- Exclusions: work you are not providing ("Excludes painting of exposed conduit").
- Clarifications: how you read an unclear document ("Ceiling height in Corridor 104 priced at 9'-0" per A301; reflected ceiling plan shows 10'-0"").
- Assumptions: conditions your price depends on ("Assumes two mobilizations; additional mobilizations at $1,850 each").
Keep these separate. A reviewer wants to see quickly what is missing (exclusions) and what might cost more later (assumptions and clarifications). Label each group clearly so nobody has to hunt.
Step by step: writing clarifications and exclusions
1. Capture them while you read the plans
Keep a running list during plan review. Every time you hit an unclear note, a scope that might belong to another trade, or a product you cannot get, write it down with the sheet or spec reference. The routine is in how to read construction plans for estimating.
2. Ask first, qualify second
If a question can be answered before bid day, send an RFI through the proper channel. A clarification is a fallback for questions that did not get answered. Owners and GCs prefer a bid that matches the documents.
3. Write one item per line, in plain words
Each line covers one item and names the reference. Use the same terms the documents use. Avoid legal-sounding blanket statements. If you know who usually carries the excluded work, say so ("by mechanical contractor"), which helps the GC level and makes you look like you understand the job.
4. Put numbers on options when you can
Instead of excluding something outright, offer it as an add: "Winter protection excluded; available as an add of $14,200 if work occurs December through February." That keeps your base bid comparable and gives the reviewer a price to plug that is yours, not their guess. This works like an alternate bid.
5. Cut the boilerplate
Many contractors attach two pages of standard exclusions to every bid. Reviewers skip them, and some items contradict the documents. Keep a short standard list for things that truly never change (for example, "Excludes bonds unless noted") and make the rest project-specific.
6. Carry them into the contract
Your clarifications only protect you if they end up in the signed contract or subcontract. At award, ask that your proposal, or at least the exclusions list, be attached as an exhibit. Without that, the contract's scope language and the documents usually govern.
Worked example: a plumbing sub's bid
Say a plumbing contractor bids $412,000 on a three-story apartment building. Here is what a focused list might look like. The prices are illustrative.
| Type | Text |
|---|---|
| Inclusion | Includes all addenda 1 through 3. |
| Inclusion | Includes water heaters per schedule on P601, including expansion tanks. |
| Exclusion | Excludes site utilities beyond 5 feet outside the building line (by civil contractor per C401). |
| Exclusion | Excludes firestopping of plumbing penetrations; available as an add of $9,600. |
| Exclusion | Excludes concrete cutting and patching for underslab work in existing slab areas. |
| Clarification | Fixture F-7 priced as the first listed manufacturer in spec 22 40 00; second manufacturer adds $1,100. |
| Assumption | Assumes one water service test and one inspection per floor; additional inspections at $420 each. |
| Assumption | Price held 60 days from bid date due to copper pricing. |
Eight lines, each tied to the documents. A GC leveling this against two other plumbing bids can plug the firestopping add directly, and knows the site utility line is with the civil contractor. Compare that with "Excludes all cutting, patching, firestopping, sitework, permits, and anything not shown" which forces the GC to guess, usually high. More on how reviewers read these in how to level subcontractor bids.
Items that often need a line
Some scope lands between trades on almost every job. If the documents do not assign it clearly, address it in your list one way or the other:
- Firestopping and sealants at penetrations.
- Cutting, patching, and painting around your work.
- Temporary power, heat, water, and hoisting.
- Permits, inspections, and testing fees.
- Equipment connections between mechanical and electrical trades.
- Overtime, phasing, and number of mobilizations.
- Bonds, special insurance, and price hold periods.
Exclusions on public bids
Sealed public bids are different. Federal rules say that to be considered for award, a bid must comply in all material respects with the invitation for bids (FAR 14.301), and a bid on the bidder's own terms can be considered only if it accepts all of the invitation's terms. Adding exclusions or conditions to a sealed public bid can make it nonresponsive. State and local agencies have similar rules. Ask questions during the question period and bid the documents as written. Subcontractors bidding to a GC on a public job can still qualify their quote to the GC, but the GC cannot pass those qualifications through to the agency. See how to bid public construction projects.
Mistakes to avoid
- Blanket exclusions. "Anything not shown" is unenforceable in spirit and annoying in practice.
- Excluding work the documents clearly assign to you. The reviewer will plug it, and you may lose a job you could have priced.
- Contradicting your own inclusions, such as including addenda but excluding work that an addendum added.
- Too many lines. Thirty exclusions read as a risky bidder.
- Not getting them into the contract. If the subcontract does not reference your proposal, the exclusions may not survive.
Related reading
Clarifications sit inside a larger proposal, covered in how to write a construction proposal that wins. They also protect you from scope gaps that turn into disputes later. Smart Business Automator keeps your proposal and its exclusions with the job record, so the project team sees what was and was not priced when the job starts. See estimate to project handoff automation.
Frequently asked questions
What is the difference between a clarification and an exclusion?
An exclusion removes work from your price. A clarification explains how you interpreted an unclear part of the documents, so the reader knows what you priced.
How many exclusions should a bid have?
As few as needed to make the price clear. A short, project-specific list gets read. Pages of boilerplate get skipped or treated as risk.
Can I add exclusions to a public bid?
Usually not on a sealed bid to a public agency. Conditions that vary the solicitation's terms can make the bid nonresponsive. Use the formal question process instead.
Do bid exclusions carry into the contract?
Only if the contract includes them, usually by attaching your proposal or listing the exclusions as an exhibit. Ask for that at award.