Baseline schedule vs current schedule
The baseline schedule is the approved plan frozen at the start of the job. The current schedule is the updated forecast showing actual progress and where the job is heading. You manage from the current schedule and measure against the baseline.
A baseline schedule is the version of the project schedule that was agreed and accepted at the start of the job, saved and never edited. The current schedule (also called the update or the working schedule) is the same schedule with actual start and finish dates, remaining durations, and logic changes added at each update. The baseline answers what did we plan. The current schedule answers where are we now and when will we finish. The gap between them is your schedule variance, and it is what owners, lenders, and claims experts look at first.
Baseline vs current schedule at a glance
| Baseline schedule | Current schedule | |
|---|---|---|
| Purpose | Fixed yardstick for measuring progress and delay | Live forecast for running the job |
| When created | At the start, after review and acceptance | At every update, weekly or monthly |
| Changes | Not edited; replaced only by a formal re-baseline | Updated with actuals, remaining durations, and logic changes |
| Dates shown | Planned start and finish | Actual dates for finished work, forecast dates for the rest |
| Who uses it | Owner, PM, scheduler, claims reviewers | Superintendent, subs, PM, owner |
| Key question | Are we where we said we would be? | What do we do next, and when will we finish? |
Why you need both
Without a baseline, you cannot prove a delay. If the only schedule you keep is the current one and you overwrite it every week, there is no record of the original plan to show that an owner's late design change pushed the finish. Without a current schedule, the baseline is a wish list. The field needs today's dates, not dates from four months ago.
Public owners lean on this. U.S. Army Corps of Engineers Engineering and Construction Bulletin 2008-23 requires the contractor to status the schedule at least monthly and calls for a current and accurate schedule to prove contractor entitlement to time extensions and government entitlement to liquidated damages. On federal fixed-price work, FAR 52.236-15 also requires the contractor to enter actual progress on the schedule when the contracting officer directs.
How to set and use a baseline in 6 steps
- Build and review the schedule. Durations, logic, procurement, and inspections, walked through with the super and major subs. See how to build a construction schedule.
- Get it accepted. Submit to the owner if the contract requires, address comments, and get written acceptance.
- Save the baseline. Most scheduling software can store a baseline copy of each activity's planned dates. In a spreadsheet, save a locked copy with the date in the file name.
- Update the current schedule on a fixed rhythm. Enter actual dates and remaining durations, then recalculate. How to update a construction schedule every week covers the routine.
- Compare at every update. Look at the variance on the finish date and on key milestones, and at which activities slipped and why.
- Re-baseline only with a reason. When a major change order or approved time extension changes the plan, save a new baseline with owner agreement, and keep the old one.
Worked example: reading the variance
Say a GC is building a two-story medical office. At month four, the scheduler compares the current schedule to the baseline for five milestones.
| Milestone | Baseline finish | Current finish | Variance (working days) |
|---|---|---|---|
| Foundations complete | Feb 14 | Feb 14 (actual) | 0 |
| Structure complete | Mar 21 | Mar 28 (actual) | 5 late |
| Dry-in | Apr 25 | May 9 (forecast) | 10 late |
| Rough-in inspections | Jun 13 | Jun 27 (forecast) | 10 late |
| Substantial completion | Sep 26 | Oct 10 (forecast) | 10 late |
Structure finished a week late, and dry-in is forecast two weeks late because the storefront submittal sat with the architect for an extra week on top of the steel delay. The baseline shows exactly when and where the slip started, which matters because the steel delay was the GC's own and the submittal delay was not. The GC sends notice for the review delay, adds it to the schedule as its own activity, and starts a recovery plan for the steel portion. Without the baseline, the two causes would blur into one 10-day slip with nobody able to split it.
Other schedule versions you will hear about
Baseline and current are the two that matter week to week, but disputes and owner reports bring in a few more names.
- As-planned: the original accepted plan. On most jobs it is the first baseline.
- As-built: the record of when every activity actually started and finished, built from the final update and the daily logs. It is the end state of the current schedule.
- Impacted or fragnet schedule: a copy of an update with a delay event added as new activities, used to show how one event moved the finish.
- Recovery schedule: a revised plan showing how a late job will get back to its required date.
- Look-ahead: a short window of the current schedule broken into crew tasks for the field.
How to show the comparison to an owner
Owners do not want a 600-activity printout. Give them a one-page milestone table like the one above, a bar chart showing baseline bars and current bars stacked for each milestone, and two or three sentences on what moved and why. Attach the full update only if the contract requires it. A short, honest comparison every month builds more trust than a thick report that hides the slip on page 14.
When to re-baseline
- An approved change order or time extension that moves the contract completion date.
- A major resequencing agreed with the owner, such as a new phasing plan.
- A suspension of work long enough that the old plan no longer reflects the job.
Do not re-baseline just because the job is late. That hides the slip and destroys the record you need if there is a dispute. Keep every baseline version with its date and the reason it changed.
Mistakes to avoid
- Overwriting the schedule each week with no saved baseline.
- Re-baselining quietly to make the job look on time.
- Updating dates by typing them in, so logic no longer drives the forecast.
- Reporting only the finish date variance and missing that a milestone is far behind.
- Not saving each monthly update for later delay analysis.
Templates, terms, and tools
The construction schedule template has columns for baseline and current dates side by side. Related terms: progress schedule, recovery schedule, schedule float, and variance. If you are behind, read how to recover a construction schedule.
Smart Business Automator keeps daily logs, change orders, and RFIs dated on each job, which gives you the record that explains why the current schedule moved away from the baseline. See construction workflow automation.
Frequently asked questions
Can the baseline schedule be changed?
Not by editing it. When the plan legitimately changes, such as after an approved time extension, save a new baseline with the owner's agreement and keep the old one on file.
What is schedule variance?
The difference between the baseline date and the current date for an activity or milestone. Positive or negative, it shows how far ahead or behind the plan the job is.
Is the as-planned schedule the same as the baseline?
Usually, yes. The as-planned schedule is the accepted original plan, which is the first baseline. Later baselines may replace it after approved changes.
How often should the current schedule be updated?
As often as the contract requires and the job needs. Corps of Engineers guidance calls for statusing at least monthly, and many contracts tie updates to the monthly pay application. Many contractors update weekly so the field always works from current dates.