What is a notice to owner in construction?
A notice to owner is a written notice that a subcontractor or supplier without a direct contract with the property owner serves early in a job, so it keeps the right to file a mechanics lien if it is not paid.
A notice to owner (NTO) is how a subcontractor or supplier introduces itself to a property owner it never signed a contract with. The message is simple: we are furnishing labor or materials to your project, and if we are not paid, we can claim a lien on your property. In Florida, where the term is used in the statute, skipping the notice or sending it late is a complete defense against the sub's lien.
Other states call the same idea a preliminary notice, a notice of furnishing, or a pre-lien notice. The concept is the same. The deadlines, recipients, and forms are not.
Florida's notice to owner rules
Section 713.06 of the Florida Statutes covers lienors who are not in privity with the owner. The key points:
- Who sends it: all lienors under the section except laborers, which covers subs, sub-subs, and suppliers who do not contract with the owner directly.
- Deadline: before starting work, or no later than 45 days after first furnishing labor, services, or materials.
- Hard stop: in any event, before the owner disburses final payment after receiving the contractor's final payment affidavit.
- Copies: a sub-sub or a supplier to a sub must also serve a copy on the contractor, and on anyone the notice of commencement designates to receive copies.
- Consequence: failing to serve it, or serving it late, is a complete defense to enforcement of the lien.
Serving the notice does not replace recording a claim of lien. It only preserves the right to record one later.
A worked example
Say a tile supplier starts delivering to a 40-unit condo project in Orlando on May 1. Its first delivery date starts the 45-day count, so the notice must be served by June 15. The supplier's credit manager pulls the recorded notice of commencement, finds the owner, the GC, the lender, and the designated notice agent, and serves all of them by a method that gives proof of delivery.
In November, the tile sub that bought the material stops paying. Because the supplier's notice was on time, it still has lien rights against the property, even though it never had a contract with the owner or the GC. The owner now has a reason to make sure the tile sub gets paid out of the next draw, often through a joint check agreement.
Common mistakes and disputes
- Counting from the wrong date. The clock starts at first furnishing, not when the invoice goes out.
- Serving only the owner and missing the contractor or the lender listed in the notice of commencement.
- Using names from the job sign instead of the recorded documents.
- Treating the NTO as an insult to the GC. It is routine on Florida jobs, and experienced GCs expect it.
- Assuming a direct contractor needs one. Florida's rule is aimed at lienors not in privity with the owner.
Related terms
The notice to owner works with the mechanics lien, lien waivers, and the notice of intent to lien that may follow if payment stops. For the step-by-step process, see how to send a preliminary notice. Smart Business Automator tracks first-furnishing dates and notice deadlines by sub and supplier through subcontractor compliance automation.
Frequently asked questions
Is a notice to owner the same as a lien?
No. It is an early notice that preserves the right to file a lien later. A lien is a separate document recorded in the county records.
What is the deadline for a Florida notice to owner?
Before starting work or within 45 days after first furnishing labor, services, or materials, and in any case before the owner makes final payment after receiving the contractor's final affidavit.
Does the general contractor send a notice to owner?
Generally no. The Florida rule targets lienors who are not in privity with the owner, such as subs, sub-subs, and suppliers.
What happens if the notice is late?
Under Florida law, failure to serve the notice, or to serve it on time, is a complete defense to enforcement of the lien.