What is estimate at completion in construction?
Estimate at completion (EAC) is the forecast of what a job will have cost in total when it is done: cost spent so far plus the cost still needed to finish. Compare it to the revised budget to see if the job is heading over budget. Under percentage of completion, percent complete equals cost to date divided by EAC.
Estimate at completion (EAC) is the projected final cost of a project or cost line. The most practical way to get it is simple addition: actual cost to date plus a bottom-up cost to complete. Compare EAC to the revised budget and you know whether the job is heading over or under. Compare it to the contract value and you know the expected gross profit.
EAC drives the percentage of completion method: percent complete equals cost to date divided by EAC. That makes it the hinge of every WIP report.
Three ways to calculate EAC
| Method | Formula | Best used when |
|---|---|---|
| Bottom-up | Actual cost plus a new cost to complete | Most construction jobs; the PM re-forecasts each line |
| Performance-based | Budget at completion divided by CPI | Work is repetitive and past efficiency is a fair guide |
| Budget-based | Actual cost plus remaining budget | Early in a job, or for lines with no variance yet |
The budget-based method is the most common and the most dangerous, because it assumes the rest of the job will go exactly to plan. Use it only where that assumption is defensible, such as a sub line that is fully bought out with no open issues.
How EAC works on a real job
A general contractor is halfway through a $3.4 million restaurant build-out with a $3.06 million cost budget. Here is the month-end review on three lines:
| Line | Budget | Cost to date | Cost to complete | EAC | Variance |
|---|---|---|---|---|---|
| Site concrete | $180,000 | $171,000 | $22,000 | $193,000 | $13,000 over |
| Kitchen equipment (sub) | $410,000 | $205,000 | $205,000 | $410,000 | On budget |
| General conditions | $240,000 | $132,000 | $138,000 | $270,000 | $30,000 over |
General conditions is running over because the job is three weeks late, and every extra week of supervision, trailer, and dumpsters adds cost. That $30,000 is real money, and it belongs in the EAC now, even if the GC hopes to recover it with a change order later. A pending recovery goes on the revenue side only when it is probable, not on the cost side as a credit.
Common EAC mistakes
- Holding EAC at budget until the job is over, then taking the whole fade in one month.
- Netting expected change order revenue against cost. Keep cost and revenue separate.
- Ignoring open commitments. A sub with $80,000 left on its contract and a pending $12,000 claim is a $92,000 cost to complete, not $80,000.
- One person forecasting every job. Have each PM own their EAC and walk through it in a monthly review.
Related terms
EAC pairs with earned value, budget variance, committed cost, overbilling, and underbilling. Smart Business Automator's job costing and WIP views show EAC by line and how it changed since last month.
Frequently asked questions
What is the difference between EAC and ETC?
ETC (estimate to complete) is the cost still to be spent. EAC is the total: actual cost to date plus ETC. In construction, ETC is usually called cost to complete.
How often should EAC be updated?
At least monthly at WIP close. Jobs with problems deserve a weekly look.
Can EAC go down?
Yes. If a buyout comes in under budget or a contingency is not needed, EAC drops and projected profit rises. Be as honest about good news as bad.
What is VAC?
Variance at completion: budget at completion minus EAC. A negative VAC means the job is forecast over budget.