What is design development in construction?
Design development (DD) is the middle phase of design, where the architect and engineers turn the approved schematic layout into real systems, sizes, and materials before final construction documents. It settles the structural, mechanical, and electrical approach and wall and window types. For a contractor, the DD set is often the first set that can carry a serious estimate.
Design development is the second of the three classic design phases: schematic design, design development, and construction documents. In schematic design, the team agrees on the footprint, the massing, and the general layout. In design development, they decide how it actually works: the structural system, the mechanical and electrical approach, the wall types, window systems, finishes, and major equipment. The drawings get bigger, the outline specifications get real, and the owner signs off on the direction.
For a contractor, the DD set is often the first set that can carry a serious estimate. It is not buildable yet. It is priceable, with assumptions.
What a DD set usually includes
- Floor plans, elevations, and building sections at a larger scale than schematic design.
- Structural system and preliminary member sizes.
- Mechanical, electrical, plumbing, and fire protection concepts with major equipment and routing.
- Wall, floor, ceiling, and roof assemblies.
- Outline specifications naming materials and systems.
- Updated code analysis and life safety plans.
What it usually does not have: full details, complete schedules, coordinated MEP routing, or the fine print that turns a priced assumption into a firm number.
Trade contractors feel DD too. A mechanical sub asked for design-assist pricing at this stage is usually choosing equipment and duct routes that the engineer will later draw. Those choices become commitments, so the sub should get its assumptions in writing just like the CM does.
How contractors use design development on a real job
Say a CM at risk is hired on a $9 million medical office building. At the DD milestone, the CM's estimator prices the set, flags every place the drawings are silent, and lists assumptions: the curtain wall is a standard storefront system, not a custom unit; the rooftop units sit on curbs, not a steel dunnage platform; the exam rooms get one sink each. The owner compares the DD estimate to the budget and decides what to cut before the architect spends months detailing the expensive version.
On many CM at risk and design-build jobs, the guaranteed maximum price is set on DD or early construction documents. That makes the assumptions list a contract document in practice. If the GMP says the curtain wall is storefront and the final drawings show a custom unitized system, the difference is a change, but only if the assumption was written into the GMP exhibit.
Common mistakes and disputes
- Pricing a DD set as if it were complete. The gaps are real scope, and someone pays for them.
- Not listing assumptions and clarifications with the estimate. Without them, the owner reads the number as all-in.
- Treating DD as design-only. This is the best moment for a constructability review and value engineering, before the details lock in.
- Arguing later that the design developed. Owners often call DD-to-CD growth design refinement, not a change. The contract language and the assumptions list decide who is right.
Related terms
See delivery method, precon, construction management at risk, and design-build. For estimating from incomplete drawings, read how to estimate construction contingency.
Frequently asked questions
What comes after design development?
The construction documents phase, where the architect and engineers produce the detailed drawings and full specifications used for permitting, bidding, and building.
How complete are design development drawings?
There is no single standard. DD drawings settle the systems, sizes, and materials but leave detailing and coordination for construction documents. The owner-architect agreement defines what each phase delivers.
Can a contractor bid a lump sum on DD drawings?
It can, but the risk is high. Most contractors price DD sets with a detailed list of assumptions and an allowance or contingency for design completion.
Who approves the design development phase?
The owner. Most owner-architect agreements require owner approval of the DD documents before the architect moves to construction documents.