What is an allowance in construction?
An allowance is a placeholder dollar amount written into a construction contract for an item that has not been fully selected yet, such as tile, light fixtures, or appliances, with the final cost adjusted up or down once the choice is made.
An allowance is money carried in the contract price for something the owner has not picked yet. A kitchen remodel might carry $6,000 for tile and $4,500 for cabinet hardware and lighting. When the owner chooses, the contractor compares the real cost to the allowance and issues a change order for the difference, up or down. It lets a job get under contract before every selection is final.
Allowances are not the same as contingency. Contingency is for unknowns. An allowance is for a known item with an unknown price.
How an allowance gets reconciled
Say a homeowner signs a $185,000 remodel with a $6,000 tile allowance. They fall for a handmade tile at $9,400 for material. The contract says the allowance covers material cost only, and that overruns carry a 15 percent markup.
| Item | Amount |
|---|---|
| Allowance in contract | $6,000 |
| Actual tile cost | $9,400 |
| Overrun | $3,400 |
| Markup per contract (15 percent) | $510 |
| Change order to owner | $3,910 |
If they had picked a $4,800 tile, the contractor would owe a $1,200 credit. Whether markup applies to credits is a question the contract should answer before anyone visits a showroom.
What does an allowance cover?
This is where most fights start. Some contracts make the allowance cover material only, delivered to site. Others include installation labor. Standard general conditions such as the AIA forms spell out a split between material cost in the allowance and labor, handling, overhead, and profit in the base price, but a homegrown contract might say nothing. Write it down, line by line:
- Material only, or material plus labor?
- Does it include tax and delivery?
- Is markup applied to overruns, credits, or both?
- What is the deadline for the owner's selection, and what happens to the schedule if it is late?
- Does a more complex install (large format tile, a heavy fixture) count against the allowance or come as a separate change?
Common allowance mistakes
- Setting allowances too low to win the job. The owner sees a lower price, then gets hit with change orders, and the relationship sours.
- No selection deadline. Late choices push long lead items and stall trades.
- Tracking allowance spending in someone's head instead of on a log the owner can see.
- Forgetting labor impact. A tile that costs the same per square foot but needs a different setting method can double install time.
Related terms
Allowances sit inside the contract sum and are reconciled through change orders. Commercial jobs use them too, often for owner-selected finishes or testing. For a residential process, see how to manage allowances in residential construction and how to handle selections and allowances with homeowners. Smart Business Automator tracks allowance balances and the change orders that adjust them on each job.
Frequently asked questions
What happens to unused allowance money?
It goes back to the owner as a credit, typically through a deductive change order at reconciliation.
Is an allowance the same as a contingency?
No. An allowance covers a specific known item whose price is not set. Contingency covers unforeseen costs that nobody has identified yet.
Can a contractor mark up an allowance?
It depends on the contract. Some include overhead and profit for allowance items in the base price, others apply a markup on overruns. The contract should say which.
How many allowances should a contract have?
As few as possible. Each one is a future change order and a possible argument, so lock selections before signing when you can.